3465 W 6TH ST #50 90020

Certificate Information: 3465 W 6TH ST #50 90020

Application / Permit
21016-10000-08456
Plan Check / Job No.
B21LA06274
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
TENANT IMPROVEMENT FOR EXISTING RESTAURANT.
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 2/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 JOE VO
Corrections Issued 4/17/2021 JOE VO
Quality Review Completed 4/22/2021 KEN GILL
Disabled Access Plans Picked Up 4/28/2021 APPLICANT
Plan Check Approved 6/14/2021 JOE VO
Issued 8/13/2021 APPLICANT
Building Plans Picked Up 8/18/2021 APPLICANT
CofO in Progress 2/17/2022 SORIN CIRSTOIU
Permit Finaled 2/18/2022 ERNESTO CORRAL
CofO Issued 2/18/2022 ERNESTO CORRAL
Permit Finaled 2/18/2022 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 5/4/2021 LAMBERT GIESSINGER
Historic monument Cleared 5/4/2021 LAMBERT GIESSINGER
Eng Process Fee Ord 176,300 Cleared 5/12/2021 RENZ SORIANO
Redevelopment Project Area Cleared 5/17/2021 DAVID URITA
Comm Cor/Mini-Mall Cleared 5/19/2021 RICHARD REASER
Comm Cor/Mini-Mall Cleared 5/19/2021 RICHARD REASER
DAS Clearance Cleared 5/20/2021 JOE VO
ZA Case Cleared 5/20/2021 CHI DANG
Sewer availability Cleared 5/27/2021 RENZ SORIANO
Food Service Establishment Cleared 6/7/2021 PAWAN VERMA
Food establishment approval Cleared 6/14/2021 LACDHS APPROVED

Contact Information

Contractor Parker James B Construction Inc; Lic. No.: 573075-B 18752 GREGORY LANE      HUNTINGTON BEACH, CA 92646

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 10/1/2021 Partial Inspection SORIN CIRSTOIU
Light Gage Steel Frame 10/8/2021 Partial Approval SORIN CIRSTOIU
Drywall Nailing 10/15/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 11/5/2021 Partial Approval SORIN CIRSTOIU
Final 2/11/2022 Partial Inspection SORIN CIRSTOIU
METHANE-Final 2/11/2022 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 2/11/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 2/11/2022 Approved SORIN CIRSTOIU
T-Bar Ceiling 2/11/2022 Not Ready for Inspection SORIN CIRSTOIU
Final 2/15/2022 Conditional Approval SORIN CIRSTOIU
METHANE-Final 2/15/2022 Approved SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Approved SORIN CIRSTOIU
T-Bar Ceiling 2/15/2022 Approved SORIN CIRSTOIU