16325 W VENTURA BLVD 91436

Certificate Information: 16325 W VENTURA BLVD 91436

Application / Permit
21016-10000-08450
Plan Check / Job No.
B21LA06271
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
INTERIOR TI TO EXISTING GROCERY STORE.
Permit Issued
Issued on 11/22/2021
Issuing Office
Current Status
Permit Finaled on 8/30/2022

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 GARO TELMI
Corrections Issued 5/7/2021 GARO TELMI
Quality Review Completed 5/13/2021 MICHAEL PEREZ
Applicant returned to address corrections 6/29/2021 GARO TELMI
Applicant returned to address corrections 8/12/2021 GARO TELMI
Applicant returned to address corrections 9/17/2021 GARO TELMI
Disabled Access Plans Picked Up 10/5/2021 APPLICANT
Plan Check Approved 10/13/2021 GARO TELMI
Issued 11/22/2021 APPLICANT
Building Plans Picked Up 12/6/2021 APPLICANT
Permit Finaled 6/21/2022 CAMERON CHABAN

Permit Application Clearance Information

DAS Clearance Cleared 7/1/2021 GARO TELMI
Green Code Cleared 7/1/2021 GARO TELMI
Specific Plan Cleared 7/27/2021 CORREY KITCHENS
Food Service Establishment Cleared 9/7/2021 JASH PATEL
Food establishment approval Cleared 9/17/2021 LACDHS APPROVED

Contact Information

Architect Smith,, Mitchell C; Lic. No.: C27800 MG2 CORPORATION   1101 2ND AVE. STE. 100    SEATTLE, WA 98101
Contractor C S I Construction Co; Lic. No.: 710391-B 27216 BURBANK      FOOTHILL RANCH, CA 92610
Engineer Habliston,, Alex Douglas; Lic. No.: S6694 13328 NE 20TH ST STE 100      BELLEVUE, WA 98005

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/17/2021 Partial Approval CAMERON CHABAN
Deputy Steel/Welding 12/22/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/22/2021 Approved DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 1/10/2022 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 1/13/2022 Partial Approval ROBERT DAVIS
Drywall Nailing 1/18/2022 Not Ready for Inspection JEFFREY FULTON
T-Bar Ceiling 2/15/2022 Not Ready for Inspection CAMERON CHABAN
T-Bar Ceiling 2/17/2022 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 2/23/2022 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/2/2022 Conditional Approval CAMERON CHABAN
Final 4/12/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Final 4/12/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 4/12/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 4/12/2022 Not Ready for Inspection JEFFREY FULTON
Final 6/21/2022 Permit Finaled CAMERON CHABAN
Green Building Final 6/21/2022 Partial Inspection CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Approved CAMERON CHABAN
Smoke Detectors 6/21/2022 Approved CAMERON CHABAN
Green Building Final 6/23/2022 Approved CAMERON CHABAN