8234 W 3RD ST 90048

Certificate Information: 8234 W 3RD ST 90048

Application / Permit
21016-10000-08413
Plan Check / Job No.
B21LA06203
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Take Out
Work Description
eplan. Change of Use from retail to Take Out Restaurant(671 SF).new store front. "operation time 7 am - 11 pm".
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 LARRY LEE
Corrections Issued 4/26/2021 LARRY LEE
Quality Review Completed 4/27/2021 SAI KHUM
Applicant returned to address corrections 6/11/2021 LARRY LEE
Plan Check Approved 6/14/2021 LARRY LEE
Issued 9/17/2021 APPLICANT
TCO Issued (Expire Date: 12-14-2022) 6/17/2022 TED RIES
TCO Issued (Expire Date: 09-24-2023) 3/28/2023 ERNESTO CORRAL
CofO in Progress 1/2/2024 JEROME BLACKWOOD
Permit Finaled 1/3/2024 ERNESTO CORRAL
CofO Issued 1/3/2024 ERNESTO CORRAL
Permit Finaled 1/3/2024 ERNESTO CORRAL

Permit Application Clearance Information

CPC Cleared 5/14/2021 MINDY NGUYEN
Comm Cor/Mini-Mall Cleared 5/18/2021 MINDY NGUYEN
Eng Process Fee Ord 176,300 Cleared 6/1/2021 CECILIO NAVARRO
Sewer availability Cleared 6/1/2021 CECILIO NAVARRO
Food Service Establishment Cleared 6/2/2021 JASH PATEL
Food establishment approval Cleared 6/11/2021 LACDHS APPROVED

Contact Information

Contractor Together Construction; Lic. No.: 1018331-B 12252 MEADOW DR      ARTESIA, CA 90701

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/2/2021 Partial Approval KATY RAMIREZ
Final 5/24/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 5/24/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 5/24/2022 Approved KATY RAMIREZ
Pre-Inspection 6/1/2022 Partial Inspection KATY RAMIREZ
Final 6/8/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV No Gas KATY RAMIREZ
Special/Order Compliance 11/16/2022 Not Ready for Inspection KATY RAMIREZ
Final 4/4/2023 Conditional Approval JEROME BLACKWOOD
Special/Order Compliance 8/29/2023 Partial Inspection JEROME BLACKWOOD
Final 1/2/2024 OK to Issue CofO JEROME BLACKWOOD