11248 W RUNNYMEDE ST 91352
Certificate Information: 11248 W RUNNYMEDE ST 91352
- Application / Permit
- 21016-10000-08401
- Plan Check / Job No.
- B21LA06190
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
- Permit Issued
- Issued on 10/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/7/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 5/12/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/9/2021 | GEORGE ALVAREZ |
| Issued | 10/3/2021 | APPLICANT |
| Building Plans Picked Up | 10/20/2021 | APPLICANT |
| CofO in Progress | 3/2/2026 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 3/17/2026 | RUBEN SALAS |
| CofO Issued | 3/17/2026 | RUBEN SALAS |
| Permit Finaled | 3/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/9/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Ramirez Construction Co; Lic. No.: 1023300-B | 2636 PINE PL SOUTH GATE, CA 90280 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2021 | Approved | DANIEL DREW |
| Sewer | 11/19/2021 | Approved | DANIEL DREW |
| Underground Mechanical | 11/19/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 12/7/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 12/7/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/7/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 12/14/2021 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/14/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/14/2021 | Corrections Issued | MISAEL ESPARZA |
| FLOOD-Proofing Certificate | 12/17/2021 | Partial Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/17/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 12/17/2021 | Approved | MISAEL ESPARZA |
| Insulation | 12/17/2021 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Approved | JACK KARGODORIAN |
| Wood Frame | 12/22/2021 | Approved | JACK KARGODORIAN |
| Insulation | 12/27/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/27/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/29/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 12/29/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/29/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/3/2022 | Conditional Approval | MISAEL ESPARZA |
| FLOOD-Proofing Certificate | 2/3/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 2/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/3/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/3/2022 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 2/3/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/8/2022 | Approved | MISAEL ESPARZA |
| HVAC-Final | 2/8/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 2/8/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/7/2022 | Not Ready for Inspection | JOHN HAYES |
| FLOOD-Proofing Certificate | 3/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 3/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 3/7/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/7/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 3/7/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| FLOOD-Proofing Certificate | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| FLOOD-Elevation Certificate | 2/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| FLOOD-Proofing Certificate | 2/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/27/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/27/2026 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |