21601 W ERWIN ST 91367
Certificate Information: 21601 W ERWIN ST 91367
- Application / Permit
- 21016-10000-08342
- Plan Check / Job No.
- B21LA06144
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. USING 11 MOMENT FRAMES AND 12 STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 7/19/2021
- Issuing Office
- Current Status
- CofC Issued on 12/28/2021
Permit Application Status History
| Submitted | 4/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | VARAND SARKISIAN |
| Corrections Issued | 4/27/2021 | VARAND SARKISIAN |
| Quality Review Completed | 4/30/2021 | HANS SANTIAGO |
| Building Plans Picked Up | 5/4/2021 | APPLICANT |
| Applicant returned to address corrections | 6/7/2021 | VARAND SARKISIAN |
| Applicant returned to address corrections | 6/9/2021 | VARAND SARKISIAN |
| Plan Check Approved | 7/14/2021 | VARAND SARKISIAN |
| Issued | 7/19/2021 | APPLICANT |
| OK for CofC | 12/16/2021 | KENNETH ROBERTS |
| CofC Issued | 12/28/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/14/2021 | SHIRLEY ZAMORA |
| Tenant Habitability Plan | Cleared | 7/13/2021 | MICHAEL SOTO |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 11949 DARBY AVE PORTER RANCH, CA 91326 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/23/2021 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 7/29/2021 | Partial Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 7/30/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/2/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/4/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/4/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/5/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/5/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/5/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/6/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/6/2021 | Conditional Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 8/9/2021 | Approved | KENNETH ROBERTS |
| Structural Steel Frame | 8/9/2021 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 8/9/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/10/2021 | Conditional Approval | KENNETH ROBERTS |
| Structural Steel Frame | 8/12/2021 | Approved | KENNETH ROBERTS |
| Wood Frame | 8/12/2021 | Approved | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/13/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/16/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/17/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/18/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/19/2021 | Conditional Approval | KENNETH ROBERTS |
| Wood Frame | 8/20/2021 | Partial Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/23/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/25/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/25/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 8/26/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/26/2021 | Conditional Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 8/26/2021 | Partial Approval | KENNETH ROBERTS |
| Insulation | 8/26/2021 | Partial Approval | KENNETH ROBERTS |
| Structural Steel Frame | 8/26/2021 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 8/26/2021 | Partial Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 8/27/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 8/30/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 8/31/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 9/1/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 9/2/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 9/3/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 9/3/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 9/3/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 9/7/2021 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 9/7/2021 | Conditional Approval | KENNETH ROBERTS |
| Footing/Foundation/Slab | 9/7/2021 | Partial Approval | KENNETH ROBERTS |
| Insulation | 9/7/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Structural Steel Frame | 9/7/2021 | Partial Approval | KENNETH ROBERTS |
| Wood Frame | 9/7/2021 | No Access for Inspection | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 9/8/2021 | Conditional Approval | KENNETH ROBERTS |
| Insulation | 9/8/2021 | Approved | KENNETH ROBERTS |
| Structural Steel Frame | 9/8/2021 | Approved | KENNETH ROBERTS |
| Wood Frame | 9/8/2021 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 9/10/2021 | Partial Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 9/28/2021 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 10/8/2021 | Approved | ALAN NOVAK |
| Interior/Exterior Lathing | 10/26/2021 | Approved | KENNETH ROBERTS |
| Drywall Nailing | 11/2/2021 | Partial Approval | KENNETH ROBERTS |
| Interior/Exterior Lathing | 11/8/2021 | Partial Approval | KENNETH ROBERTS |
| Final | 12/16/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 12/16/2021 | Approved | KENNETH ROBERTS |