1506-1506 1/2 S 5TH AVE 90019
Certificate Information: 1506-1506 1/2 S 5TH AVE 90019
- Application / Permit
- 21016-10000-08252
- Plan Check / Job No.
- B21LA06056
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (2) Duplex
- Work Description
- FRONT BUILDING: CHANGE OF USE FROM DUPLEX TO DUPLEX & ADU AT 1ST FLOOR. INTERIOR REMODEL "COMPLY WITH DEPARTMENT ORDER effective date 12/10/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector GLEN RAND at (213)252-3957 of GENERAL ENFORCEMENT SOUTH. CEIS Case Number is 940914.
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | PRANITA SHAH |
| Corrections Issued | 4/28/2021 | PRANITA SHAH |
| Plans on Hold | 5/6/2021 | MICHAEL PEREZ |
| Hold Released | 5/13/2021 | MICHAEL PEREZ |
| Quality Review Completed | 5/13/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 5/14/2021 | APPLICANT |
| Applicant returned to address corrections | 7/8/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 9/2/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 10/4/2021 | PRANITA SHAH |
| Plan Check Approved | 12/21/2021 | PRANITA SHAH |
| Issued | 12/21/2021 | APPLICANT |
| Permit Finaled | 4/11/2024 | WINSTON DUNNING |
| CofO Issued | 4/11/2024 | WINSTON DUNNING |
| Permit Finaled | 4/11/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Hold | Cleared | 4/28/2021 | JASON SHEETS |
| Address approval | Cleared | 6/14/2021 | CELINA MORENO |
| Sewer availability | Cleared | 6/14/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | CELINA MORENO |
| Community Plan Implem. Overlay | Cleared | 10/28/2021 | KYLE WINSTON |
Contact Information
| Contractor | Blue Phoenix Builders Inc; Lic. No.: 1066549-B | 4474 W ADAMS BLVD #205 LOS ANGELES, CA 90016 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 6/14/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 6/14/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| METHANE-Rough | 9/12/2022 | Approved | TIMOTHY BUXTON |
| Wood Frame | 9/12/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 9/23/2022 | Approved | TIMOTHY BUXTON |
| Wood Frame | 4/19/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 5/2/2023 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 5/16/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Insulation | 5/18/2023 | Approved | RAFAEL CORTES |
| Drywall Nailing | 5/30/2023 | Approved | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 6/16/2023 | Approved | RAMAZANALI ALMASI |
| Final | 3/21/2024 | Corrections Issued | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 3/21/2024 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 3/21/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 3/21/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Final | 4/1/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 4/1/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 4/1/2024 | Approved | JEROME BLACKWOOD |
| Final | 4/5/2024 | Conditional Approval | DARRYL ARNOLD |
| Smoke Detectors | 4/5/2024 | Conditional Approval | DARRYL ARNOLD |