2755 N KNOX AVE 90039

Certificate Information: 2755 N KNOX AVE 90039

Application / Permit
21016-10000-08245
Plan Check / Job No.
B21LA06049
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/30/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2021 APPLICANT
Assigned to Plan Check Engineer 5/6/2021 DANIEL YIP
Corrections Issued 5/11/2021 DANIEL YIP
Quality Review Completed 5/14/2021 JASON HEALEY
Building Plans Picked Up 5/21/2021 APPLICANT
Plan Check Approved 6/22/2023 DANIEL YIP
Issued 6/30/2023 APPLICANT
CofO in Progress 4/17/2025 HAMIK HARTOUNIAN
Permit Finaled 4/18/2025 DEROLD HAUFF
CofO Issued 4/18/2025 DEROLD HAUFF
Permit Finaled 4/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/14/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 1/13/2022 CINDY QI
Sewer availability Cleared 1/13/2022 CINDY QI

Contact Information

Contractor Gaeta Jose Luis; Lic. No.: 809569-B 2251 WENSLEY AVE      EL CENTRO, CA 92243
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 10/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Final 10/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 10/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 10/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 11/18/2024 Not Ready for Inspection LUIS CASTRO
Final 11/18/2024 Not Ready for Inspection LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 11/18/2024 Not Ready for Inspection LUIS CASTRO
Wood Frame 11/18/2024 Not Ready for Inspection LUIS CASTRO
Pre-Inspection 2/7/2025 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 4/1/2025 Approved HAMIK HARTOUNIAN
Final 4/1/2025 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/1/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 4/1/2025 Approved HAMIK HARTOUNIAN
Wood Frame 4/1/2025 Approved HAMIK HARTOUNIAN
Final 4/10/2025 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/10/2025 SGSOV Approved HAMIK HARTOUNIAN
Final 4/14/2025 Corrections Issued HAMIK HARTOUNIAN
Final 4/17/2025 OK to Issue CofO HAMIK HARTOUNIAN