7842 S BRIGHTON AVE 90047
Certificate Information: 7842 S BRIGHTON AVE 90047
- Application / Permit
- 21016-10000-08169
- Plan Check / Job No.
- B21LA05992
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITON OF FRONT PORCH AND REAR PATIO.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 4/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2021 | RAMA DABADGE |
| Corrections Issued | 4/23/2021 | RAMA DABADGE |
| Applicant returned to address corrections | 7/22/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 9/21/2021 | DANIEL SANJUAN |
| Plan Check Approved | 10/21/2021 | RICARDO RAMIREZ |
| Issued | 12/2/2021 | APPLICANT |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| CofO in Progress | 8/2/2023 | MICHAEL LEWIS |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
| CofO Issued | 4/5/2025 | DEROLD HAUFF |
| Permit Finaled | 4/5/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/9/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2021 | CELINA MORENO |
Contact Information
| Contractor | Sao Nissay; Lic. No.: 1035354-B | 3450 ADRIATIC AVE LONG BEACH, CA 90810 |
| Engineer | Dang,, Jennifer Li; Lic. No.: C82695 | 701 E CARSON STREET CARSON, CA 90745 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 12/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/15/2021 | No Access for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 12/15/2021 | No Access for Inspection | ADAM ESCOTO |
| Footing/Foundation/Slab | 12/15/2021 | No Access for Inspection | ADAM ESCOTO |
| HVAC-Rough | 12/15/2021 | No Access for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 12/15/2021 | No Access for Inspection | ADAM ESCOTO |
| Rough-Elec/Plmb/HVAC | 12/15/2021 | No Access for Inspection | ADAM ESCOTO |
| BUILDING-Rough-Frame | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| ELECTRICAL-Rough | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Footing/Foundation/Slab | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| HVAC-Rough | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| PLUMBING-Rough | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Rough-Elec/Plmb/HVAC | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Wood Frame | 12/20/2021 | Not Ready for Inspection | ADAM ESCOTO |
| BUILDING-Rough-Frame | 1/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 1/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 1/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| Wood Frame | 1/24/2022 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/28/2022 | Not Ready for Inspection | HORACE FULTZ |
| HVAC-Rough | 1/28/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 1/28/2022 | Not Ready for Inspection | HORACE FULTZ |
| Wood Frame | 1/28/2022 | Not Ready for Inspection | HORACE FULTZ |
| Footing/Foundation/Slab | 2/2/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 2/3/2022 | No Access for Inspection | LILIANA PORTILLO |
| Wood Frame | 2/3/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 2/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/30/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/30/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/4/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 4/5/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/8/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/13/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/13/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/13/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 4/13/2022 | Approved | LILIANA PORTILLO |
| Insulation | 5/24/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 6/1/2022 | Conditional Approval | LILIANA PORTILLO |
| Drywall Nailing | 6/22/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Drywall Nailing | 6/24/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 6/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 7/1/2022 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/16/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/21/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/30/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/6/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/5/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Final | 6/5/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/5/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/5/2023 | No Access for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | STUART CHAPMAN |
| Final | 6/9/2023 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 6/9/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/20/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 7/20/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Final | 7/20/2023 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Final | 7/20/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 7/31/2023 | Approved | MICHAEL LEWIS |
| Final | 7/31/2023 | OK to Issue CofO | MICHAEL LEWIS |
| HVAC-Final | 7/31/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 7/31/2023 | Partial Inspection | MICHAEL LEWIS |