673-675 W 61ST ST 90044
Certificate Information: 673-675 W 61ST ST 90044
- Application / Permit
- 21016-10000-08132
- Plan Check / Job No.
- B21LA05967
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Conversion of second floor (729 sf) of an (E) 2-story duplex into an ADU per ordinance 186,481.
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | HELEN NGUYEN |
| Corrections Issued | 4/27/2021 | HELEN NGUYEN |
| Quality Review Completed | 5/4/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 5/6/2021 | APPLICANT |
| Applicant returned to address corrections | 9/17/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 2/22/2022 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/3/2022 | HELEN NGUYEN |
| Plan Check Approved | 5/5/2022 | HELEN NGUYEN |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 3/8/2024 | JOSEPH MCGARRY |
| CofO Issued | 3/18/2024 | DEROLD HAUFF |
| Permit Finaled | 3/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 1/21/2022 | ANACANY HURTADO |
| Sewer availability | Cleared | 2/8/2022 | STEVE MELGAR |
| Address approval | Cleared | 3/18/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2023 | Corrections Issued | BRENDAN MORELLI |
| Wood Frame | 1/23/2023 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 1/27/2023 | Approved | BRENDAN MORELLI |
| Pre-Inspection | 2/28/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 3/1/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | JOSEPH MCGARRY |
| Final | 3/7/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 3/7/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 3/7/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 3/7/2024 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 3/7/2024 | Approved | JOSEPH MCGARRY |