16554-16556 W BIRCHER ST 91344

Certificate Information: 16554-16556 W BIRCHER ST 91344

Application / Permit
21016-10000-08085
Plan Check / Job No.
B21LA05946
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED GARAGE TO ADU PER WFPP (GCS 65852.2(e)(1)(A), ATTACHED ADU CONTAINED IN EXISTING SFD PER STATE LAW)
Permit Issued
Issued on 7/20/2021
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/5/2021 RACHEL BEYENE
Corrections Issued 5/5/2021 RACHEL BEYENE
Applicant returned to address corrections 7/11/2021 AUNG SOE
Plan Check Approved 7/12/2021 AUNG SOE
Building Plans Picked Up 7/14/2021 APPLICANT
Issued 7/20/2021 APPLICANT
CofO in Progress 12/20/2022 JAVIER RAMOS JR
Permit Finaled 12/24/2022 MICHAEL SMITH
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/21/2021 BRIAN MILLER
Address approval Cleared 6/23/2021 CARLOS AGUILERA
Sewer availability Cleared 6/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/24/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/24/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 1/4/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 1/14/2022 Approved MARK JOHNSON
PLUMBING-Rough 1/14/2022 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 1/28/2022 Approved RAUL OLAGI
Wood Frame 1/28/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/15/2022 Corrections Issued JESUS RODRIGUEZ
Gas Test 2/15/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 2/15/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 2/15/2022 Conditional Approval JESUS RODRIGUEZ
Gas Test 4/27/2022 Partial Approval JAVIER RAMOS JR
Insulation 4/27/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 4/27/2022 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 4/27/2022 Partial Approval MICHAEL TEMPLE
Shower Pan 4/27/2022 Approved JAVIER RAMOS JR
Insulation 4/29/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/3/2022 Partial Approval DEANDRE HOFFMAN
Interior/Exterior Lathing 5/13/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 5/18/2022 Approved JAVIER RAMOS JR
Green Building Rough 5/18/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/18/2022 Approved JAVIER RAMOS JR
Drywall Nailing 5/24/2022 Corrections Issued RAUL OLAGI
Drywall Nailing 5/31/2022 Approved JAVIER RAMOS JR
Final 10/25/2022 Corrections Issued JAVIER RAMOS JR
Green Building Final 10/25/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/25/2022 Approved JAVIER RAMOS JR
Final 12/20/2022 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/20/2022 Approved JAVIER RAMOS JR