16554-16556 W BIRCHER ST 91344
Certificate Information: 16554-16556 W BIRCHER ST 91344
- Application / Permit
- 21016-10000-08085
- Plan Check / Job No.
- B21LA05946
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ADU PER WFPP (GCS 65852.2(e)(1)(A), ATTACHED ADU CONTAINED IN EXISTING SFD PER STATE LAW)
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2021 | RACHEL BEYENE |
| Corrections Issued | 5/5/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/11/2021 | AUNG SOE |
| Plan Check Approved | 7/12/2021 | AUNG SOE |
| Building Plans Picked Up | 7/14/2021 | APPLICANT |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 12/20/2022 | JAVIER RAMOS JR |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/21/2021 | BRIAN MILLER |
| Address approval | Cleared | 6/23/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/24/2021 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 1/4/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/14/2022 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | MARK JOHNSON |
| ELECTRICAL-Rough | 1/28/2022 | Approved | RAUL OLAGI |
| Wood Frame | 1/28/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 2/15/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 2/15/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 2/15/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Gas Test | 4/27/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 4/27/2022 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/27/2022 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 4/27/2022 | Partial Approval | MICHAEL TEMPLE |
| Shower Pan | 4/27/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 4/29/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/3/2022 | Partial Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/13/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/18/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/18/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/18/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/24/2022 | Corrections Issued | RAUL OLAGI |
| Drywall Nailing | 5/31/2022 | Approved | JAVIER RAMOS JR |
| Final | 10/25/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/25/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 10/25/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/20/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 12/20/2022 | Approved | JAVIER RAMOS JR |