5665 W WILSHIRE BLVD 90036

Certificate Information: 5665 W WILSHIRE BLVD 90036

Application / Permit
21016-10000-07926
Plan Check / Job No.
B21LA05810
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Interior retail Tenant Improvement and restriping parking spaces,no change in total number of parking. No change of use. EXISTING EXTERIOR FACADE FINISHES TO BE REPLACED;All interior work to include new partitions, finishes, fixtures, doors, and ceiling.
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
Issued on 7/26/2021

Permit Application Status History

Submitted 4/2/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 YOUNG KIM
Corrections Issued 4/19/2021 YOUNG KIM
Quality Review Completed 4/21/2021 SAI KHUM
Applicant returned to address corrections 5/26/2021 YOUNG KIM
Applicant returned to address corrections 6/28/2021 YOUNG KIM
Applicant returned to address corrections 7/12/2021 YOUNG KIM
Plan Check Approved 7/23/2021 LAMAR DAVIS
No Progress 7/23/2021 LAMAR DAVIS
Plan Check Approved 7/23/2021 LAMAR DAVIS
Issued 7/26/2021 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 4/30/2021 CHI DANG
Supp. Use District POD/CDO/TDO Cleared 4/30/2021 CHI DANG
Green Code Cleared 5/7/2021 YOUNG KIM
Metro Rail approval Cleared 5/13/2021 SAI KHUM
DAS Clearance Cleared 6/2/2021 YOUNG KIM

Contact Information

Architect Davis,, Michael R; Lic. No.: C32117 BERGMEYER ASSOCIATES INC.   51 SLEEPER ST. 6TH FL.    BOSTON, MA 02210
Contractor Heiliger - Marsh Inc; Lic. No.: 689329-B 445 CORPORATE DRIVE #A      ESCONDIDO, CA 92029

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/28/2021 Conditional Approval TIMOTHY BUXTON
Light Gage Steel Frame 7/28/2021 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 8/3/2021 Approved TIMOTHY BUXTON
Drywall Nailing 8/6/2021 Approved TIMOTHY BUXTON
Pre-Inspection 9/7/2021 Approved KATY RAMIREZ
Pre-Inspection 9/13/2021 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 9/23/2021 Corrections Issued KATY RAMIREZ
Partition/T-Bar Ceiling 9/23/2021 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/27/2021 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 9/27/2021 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 9/28/2021 Conditional Approval KATY RAMIREZ
Interior/Exterior Lathing 10/4/2021 Approved RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 10/5/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 10/6/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 10/7/2021 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 10/8/2021 Conditional Approval RUSSELL BONVOULOIR
Final 10/8/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Green Building Final 10/8/2021 Not Ready for Inspection RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready RUSSELL BONVOULOIR
Smoke Detectors 10/8/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Pre-Inspection 10/25/2021 Partial Inspection MARK FERRARI
Final 11/3/2021 Not Ready for Inspection KATY RAMIREZ
Green Building Final 11/3/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/3/2021 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 11/3/2021 Approved KATY RAMIREZ