2552 E OLYMPIC BLVD 90023
Certificate Information: 2552 E OLYMPIC BLVD 90023
- Application / Permit
- 21016-10000-07910
- Plan Check / Job No.
- B21LA05787
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- EXPAND OFFICE SPACE IN EXISTING WAREHOUSE/MANUFACTURE
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- CofO Issued on 2/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | VU NGUYEN |
| Green Plans Picked Up | 4/30/2021 | APPLICANT |
| Corrections Issued | 5/6/2021 | VU NGUYEN |
| Quality Review Completed | 5/6/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 5/10/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 5/21/2021 | APPLICANT |
| Applicant returned to address corrections | 9/29/2021 | VU NGUYEN |
| Plan Check Approved | 12/16/2021 | VU NGUYEN |
| Issued | 2/16/2022 | APPLICANT |
| CofO in Progress | 2/13/2024 | RAMAZANALI ALMASI |
| Permit Finaled | 2/13/2024 | ERNESTO CORRAL |
| CofO Issued | 2/13/2024 | ERNESTO CORRAL |
| Permit Finaled | 2/13/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic monument | Cleared | 6/4/2021 | MICAELA TORRES-GIL |
| City Hist. Cultural Monument | Cleared | 6/7/2021 | MICAELA TORRES-GIL |
| Historic Resource Verification | Cleared | 6/7/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 6/16/2021 | GRACIELA ACOSTA |
| Green Code | Cleared | 10/5/2021 | AARON COSTA |
| DAS Clearance | Cleared | 12/14/2021 | EUGENE BARBEAU |
Contact Information
| Contractor | J M H Construction Inc; Lic. No.: 860100-B | 3528 EAST 16TH STREET LOS ANGELES, CA 90023 |
| Engineer | Hanna,, Emil R; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/26/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/26/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 10/28/2022 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 11/2/2022 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 11/2/2022 | Partial Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 11/22/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 2/8/2023 | Partial Approval | JULIAN CAPUCETTI |
| Structural Steel Frame | 2/8/2023 | Not Ready for Inspection | JULIAN CAPUCETTI |
| Deputy Drilled-In Anchors | 2/16/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 2/28/2023 | Partial Approval | JULIAN CAPUCETTI |
| Insulation | 2/28/2023 | Partial Approval | JULIAN CAPUCETTI |
| Drywall Nailing | 3/6/2023 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 4/13/2023 | Approved | JULIAN CAPUCETTI |
| Insulation | 6/12/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 6/12/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| T-Bar Ceiling | 6/14/2023 | Approved | JULIAN CAPUCETTI |
| Final | 1/26/2024 | Corrections Issued | KATY RAMIREZ |
| Green Building Final | 1/26/2024 | Approved | KATY RAMIREZ |
| Green Building Rough | 1/26/2024 | Approved | KATY RAMIREZ |
| METHANE-Final | 1/26/2024 | Approved | KATY RAMIREZ |
| METHANE-Rough | 1/26/2024 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 1/26/2024 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 2/12/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 2/12/2024 | Approved | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV No Gas | RAMAZANALI ALMASI |
| Smoke Detectors | 2/12/2024 | Approved | RAMAZANALI ALMASI |
| Final | 2/13/2024 | OK to Issue CofO | RAMAZANALI ALMASI |