3747 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3747 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21016-10000-07869
- Plan Check / Job No.
- B21LA05743
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/9/2021
- Issuing Office
- Current Status
- CofO Issued on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2021 | KEVIN MORALES |
| Corrections Issued | 4/1/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 4/12/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 4/28/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 4/29/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 4/30/2021 | KEVIN MORALES |
| Plan Check Approved | 7/1/2021 | KEVIN MORALES |
| Issued | 7/9/2021 | APPLICANT |
| CofO in Progress | 11/18/2021 | KENNETH NAGLE |
| Permit Finaled | 11/18/2021 | KENNETH NAGLE |
| CofO Issued | 11/18/2021 | KENNETH NAGLE |
| Permit Finaled | 11/18/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 4/8/2021 | RENZ SORIANO |
| ZA Case | Cleared | 4/9/2021 | ANACANY HURTADO |
| Specific Plan | Cleared | 5/9/2021 | EDUARDO HERMOSO |
Contact Information
| Architect | Olfati,, Ali; Lic. No.: NA22217 | , |
| Contractor | D C I Development Group Inc; Lic. No.: 1056455-B | 4569 VALLEY BLVD LOS ANGELES, CA 90032 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/13/2021 | Not Ready for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 7/13/2021 | Corrections Issued | KENNETH NAGLE |
| Green Building Rough | 7/13/2021 | Not Ready for Inspection | KENNETH NAGLE |
| HVAC-Rough | 7/13/2021 | Corrections Issued | KENNETH NAGLE |
| MERV13>=Rough | 7/13/2021 | Not Ready for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 7/13/2021 | Partial Approval | KENNETH NAGLE |
| Sewer | 7/13/2021 | Not Ready for Inspection | KENNETH NAGLE |
| Wood Frame | 7/13/2021 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 7/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/19/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/19/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/21/2021 | Partial Approval | KENNETH NAGLE |
| Green Building Rough | 7/21/2021 | Not Ready for Inspection | KENNETH NAGLE |
| MERV13>=Rough | 7/21/2021 | Approved | KENNETH NAGLE |
| Rough-Elec/Plmb/HVAC | 7/21/2021 | Approved | KENNETH NAGLE |
| Sewer | 7/21/2021 | Approved | KENNETH NAGLE |
| Wood Frame | 7/21/2021 | Partial Approval | KENNETH NAGLE |
| Interior/Exterior Lathing | 8/2/2021 | Conditional Approval | MORRIS JACKSON |
| Insulation | 8/4/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/4/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 8/4/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 8/12/2021 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 8/16/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 10/20/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 10/20/2021 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Final | 10/20/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 10/20/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/27/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 10/27/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 11/4/2021 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Final | 11/4/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | JOHNNY MIRANDA |