14920 W MINNEHAHA ST 91345
Certificate Information: 14920 W MINNEHAHA ST 91345
- Application / Permit
- 21016-10000-07862
- Plan Check / Job No.
- B21LA05725
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Rear addition per WFPP to existing SFD.
- Permit Issued
- Issued on 4/12/2023
- Issuing Office
- Current Status
- Issued on 4/12/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2021 | JOE VO |
| Corrections Issued | 4/9/2021 | JOE VO |
| Plan Check Approved | 4/11/2023 | JOE VO |
| Issued | 4/12/2023 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/20/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2022 | ABDULLAH SADOZAI |
| Construction near power lines | Cleared | 10/16/2022 | PATRICK MAGALLANES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/10/2023 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/10/2023 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/10/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/24/2023 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 5/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/30/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/30/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/6/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/6/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 6/6/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/6/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/14/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/31/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/31/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/31/2023 | Approved | JENNIFER RABUCHIN |