1115 E NOWITA PL 90291

Certificate Information: 1115 E NOWITA PL 90291

Application / Permit
21016-10000-07843
Plan Check / Job No.
B21LA05708
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached 21' X 21' garage to ADU
Permit Issued
Issued on 7/7/2021
Issuing Office
Current Status
CofO Issued on 6/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/30/2021 JOE VO
Corrections Issued 4/1/2021 JOE VO
Applicant returned to address corrections 4/26/2021 JOE VO
Plan Check Approved 7/1/2021 JOE VO
Issued 7/7/2021 APPLICANT
CofO in Progress 6/8/2022 JESUS RODRIGUEZ
Permit Finaled 6/9/2022 DANIEL ORRANTE
CofO Issued 6/9/2022 DANIEL ORRANTE
Permit Finaled 6/9/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/8/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 4/8/2021 DINAH GARIN
Sewer availability Cleared 4/8/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/9/2021 DINAH GARIN
Construction near power lines Cleared 6/26/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: NA53080       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Approved ENRIQUE MIRELES
Green Building Rough 12/3/2021 Not Ready for Inspection ENRIQUE MIRELES
Deputy Drilled-In Anchors 12/14/2021 No Access for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 12/15/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 12/15/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 12/15/2021 Not Ready for Inspection DAVID FEILER
Underground Mechanical 12/15/2021 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 12/20/2021 Not Ready for Inspection DAVID FEILER
Sewer 12/20/2021 Corrections Issued DAVID FEILER
Underground Mechanical 12/20/2021 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 12/21/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 12/21/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 12/21/2021 Not Ready for Inspection DAVID FEILER
Underground Mechanical 1/4/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/6/2022 Approved JOHN KAYON
Underground Mechanical 1/6/2022 Approved JOHN KAYON
BUILDING-Rough-Frame 1/21/2022 Corrections Issued DAVID FEILER
Green Building Rough 1/21/2022 Not Ready for Inspection DAVID FEILER
Deputy Wood Construction 1/24/2022 Partial Approval JOHN KAYON
Deputy Wood Construction 1/25/2022 Conditional Approval DAVID FEILER
BUILDING-Rough-Frame 2/14/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 2/14/2022 Partial Approval DAVID FEILER
HVAC-Rough 2/14/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 2/14/2022 Partial Approval DAVID FEILER
Shower Pan 2/14/2022 Approved DAVID FEILER
ELECTRICAL-Rough 2/17/2022 Approved DAVID FEILER
Green Building Rough 2/17/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 2/17/2022 Approved DAVID FEILER
PLUMBING-Rough 2/17/2022 Approved DAVID FEILER
Insulation 2/23/2022 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 2/23/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 2/28/2022 Not Ready for Inspection DAVID FEILER
Green Building Rough 2/28/2022 Not Ready for Inspection DAVID FEILER
Insulation 2/28/2022 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 3/3/2022 Approved DAVID FEILER
Green Building Rough 3/3/2022 Approved DAVID FEILER
Insulation 3/3/2022 Partial Approval DAVID FEILER
Drywall Nailing 3/8/2022 Partial Approval DAVID FEILER
Insulation 3/8/2022 Partial Approval DAVID FEILER
Drywall Nailing 3/30/2022 Approved STEPHANIE SWANSON
Insulation 3/30/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 5/16/2022 Corrections Issued STEPHANIE SWANSON
Final 5/16/2022 Corrections Issued STEPHANIE SWANSON
Green Building Final 5/16/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Final 5/16/2022 Approved STEPHANIE SWANSON
PLUMBING-Final 5/16/2022 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 5/16/2022 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 5/16/2022 Approved STEPHANIE SWANSON
Final 5/27/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 5/27/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Not Ready JESUS RODRIGUEZ
Final 6/6/2022 Partial Approval JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Approved JESUS RODRIGUEZ