1115 E NOWITA PL 90291
Certificate Information: 1115 E NOWITA PL 90291
- Application / Permit
- 21016-10000-07843
- Plan Check / Job No.
- B21LA05708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached 21' X 21' garage to ADU
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2021 | JOE VO |
| Corrections Issued | 4/1/2021 | JOE VO |
| Applicant returned to address corrections | 4/26/2021 | JOE VO |
| Plan Check Approved | 7/1/2021 | JOE VO |
| Issued | 7/7/2021 | APPLICANT |
| CofO in Progress | 6/8/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 6/9/2022 | DANIEL ORRANTE |
| CofO Issued | 6/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/8/2021 | DINAH GARIN |
| Sewer availability | Cleared | 4/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 6/26/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: NA53080 | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 12/3/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 12/14/2021 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/15/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 12/15/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/15/2021 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 12/15/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 12/20/2021 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 12/20/2021 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 12/20/2021 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 12/21/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/21/2021 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 1/4/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/6/2022 | Approved | JOHN KAYON |
| Underground Mechanical | 1/6/2022 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 1/21/2022 | Corrections Issued | DAVID FEILER |
| Green Building Rough | 1/21/2022 | Not Ready for Inspection | DAVID FEILER |
| Deputy Wood Construction | 1/24/2022 | Partial Approval | JOHN KAYON |
| Deputy Wood Construction | 1/25/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/14/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 2/14/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 2/14/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 2/14/2022 | Partial Approval | DAVID FEILER |
| Shower Pan | 2/14/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 2/17/2022 | Approved | DAVID FEILER |
| Green Building Rough | 2/17/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 2/17/2022 | Approved | DAVID FEILER |
| PLUMBING-Rough | 2/17/2022 | Approved | DAVID FEILER |
| Insulation | 2/23/2022 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/23/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/28/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 2/28/2022 | Not Ready for Inspection | DAVID FEILER |
| Insulation | 2/28/2022 | Corrections Issued | DAVID FEILER |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | DAVID FEILER |
| Green Building Rough | 3/3/2022 | Approved | DAVID FEILER |
| Insulation | 3/3/2022 | Partial Approval | DAVID FEILER |
| Drywall Nailing | 3/8/2022 | Partial Approval | DAVID FEILER |
| Insulation | 3/8/2022 | Partial Approval | DAVID FEILER |
| Drywall Nailing | 3/30/2022 | Approved | STEPHANIE SWANSON |
| Insulation | 3/30/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 5/16/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 5/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 5/16/2022 | Approved | STEPHANIE SWANSON |
| Final | 5/27/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 5/27/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Final | 6/6/2022 | Partial Approval | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | JESUS RODRIGUEZ |