980 W 190TH ST B-3 90502

Certificate Information: 980 W 190TH ST B-3 90502

Application / Permit
21016-10000-07746
Plan Check / Job No.
B21LA05655
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
CHANGE OF USE FROM RETAIL (M) TO RESTAURANT (A2) USE FOR BUILDING B, B3 SPACE. NO CHANGE IN PARKING. [NO ALCOHOL]
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 4/5/2021 ZAW HAN
Corrections Issued 4/7/2021 ZAW HAN
Quality Review Completed 4/14/2021 WING SUEN
Green Plans Picked Up 7/9/2021 APPLICANT
Applicant returned to address corrections 7/15/2021 ZAW HAN
Applicant returned to address corrections 8/26/2021 ZAW HAN
Plan Check Approved 8/30/2021 ZAW HAN
Issued 9/15/2021 APPLICANT
Building Plans Picked Up 9/16/2021 APPLICANT
CofO in Progress 3/29/2023 JOEY BUCHANAN
Permit Finaled 3/29/2023 DAVID TSAU
CofO Issued 3/29/2023 DAVID TSAU
Permit Finaled 3/29/2023 DAVID TSAU

Permit Application Clearance Information

Green Code Cleared 7/7/2021 AARON COSTA
Food establishment approval Cleared 7/15/2021 LACDHS APPROVED
DAS Clearance Cleared 7/26/2021 ZAW HAN
Miscellaneous Cleared 7/26/2021 RUBEN VASQUEZ
Miscellaneous Cleared 7/26/2021 RUBEN VASQUEZ
Miscellaneous Cleared 7/26/2021 RUBEN VASQUEZ
Miscellaneous Cleared 7/26/2021 RUBEN VASQUEZ
ZI Cleared 7/26/2021 RUBEN VASQUEZ
Food Service Establishment Cleared 8/3/2021 PAWAN VERMA
Eng Process Fee Ord 176,300 Cleared 8/20/2021 JOSE HERNANDEZ
Sewer availability Cleared 8/20/2021 JOSE HERNANDEZ

Contact Information

Architect Barany,, Donald Alec; Lic. No.: C12803 116 26TH ST      SANTA MONICA, CA 90402
Contractor Gaudenti & Sons Corporation; Lic. No.: 283650-B 231 VISTA DEL MAR      REDONDO BEACH, CA 90277

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/27/2021 Approved JOEY BUCHANAN
Footing/Foundation/Slab 10/28/2021 Corrections Issued JOEY BUCHANAN
Drywall Nailing 11/15/2021 Approved JOEY BUCHANAN
Drywall Nailing 2/28/2022 Partial Approval DAVID TSAU
T-Bar Ceiling 10/19/2022 Approved JOEY BUCHANAN
Final 1/27/2023 Not Ready for Inspection AMANUEL BERHE
Green Building Final 1/27/2023 Not Ready for Inspection AMANUEL BERHE
Green Building Rough 1/27/2023 Not Ready for Inspection AMANUEL BERHE
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Not Ready AMANUEL BERHE
Smoke Detectors 1/27/2023 Approved AMANUEL BERHE
Wood Frame 1/27/2023 Not Ready for Inspection AMANUEL BERHE
Final 2/2/2023 Not Ready for Inspection JOEY BUCHANAN
Green Building Final 2/2/2023 Approved JOEY BUCHANAN
Green Building Rough 2/2/2023 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Approved JOEY BUCHANAN
Wood Frame 2/2/2023 Approved JOEY BUCHANAN
Final 3/14/2023 Not Ready for Inspection AMANUEL BERHE
Interior/Exterior Lathing 3/16/2023 Corrections Issued JOEY BUCHANAN
Final 3/29/2023 OK to Issue CofO JOEY BUCHANAN