980 W 190TH ST A-1 90502
Certificate Information: 980 W 190TH ST A-1 90502
- Application / Permit
- 21016-10000-07744
- Plan Check / Job No.
- B21LA05653
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- CHANGE OF USE FROM RETAIL (M) TO RESTAURANT (A2) USE FOR BUILDING A, A1 SPACE. NO CHANGE IN PARKING. [NO ALCOHOL]
- Permit Issued
- Issued on 9/14/2021
- Issuing Office
- Current Status
- CofO Corrected on 4/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2021 | ZAW HAN |
| Corrections Issued | 4/7/2021 | ZAW HAN |
| Quality Review Completed | 4/14/2021 | WING SUEN |
| Disabled Access Plans Picked Up | 5/3/2021 | APPLICANT |
| Green Plans Picked Up | 7/9/2021 | APPLICANT |
| Applicant returned to address corrections | 7/15/2021 | ZAW HAN |
| Plan Check Approved | 8/30/2021 | ZAW HAN |
| Issued | 9/14/2021 | APPLICANT |
| Building Plans Picked Up | 9/16/2021 | APPLICANT |
| CofO in Progress | 3/29/2023 | JOEY BUCHANAN |
| CofO Issued-Status Void | 3/29/2023 | DAVID TSAU |
| Permit Finaled-Status Void | 3/29/2023 | DAVID TSAU |
| Re-Activate Permit | 7/10/2023 | DAVID TSAU |
| Permit Finaled | 3/31/2026 | MICHAEL PETRUSKO |
| CofO Corrected | 4/24/2026 | DAVID TSAU |
| Permit Finaled | 4/24/2026 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 7/7/2021 | AARON COSTA |
| Food establishment approval | Cleared | 7/15/2021 | LACDHS APPROVED |
| Miscellaneous | Cleared | 7/26/2021 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/26/2021 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/26/2021 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 7/26/2021 | RUBEN VASQUEZ |
| ZI | Cleared | 7/26/2021 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 7/29/2021 | ZAW HAN |
| Food Service Establishment | Cleared | 8/3/2021 | PAWAN VERMA |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 8/20/2021 | JOSE HERNANDEZ |
Contact Information
| Architect | Barany,, Donald Alec; Lic. No.: C12803 | 116 26TH ST SANTA MONICA, CA 90402 |
| Contractor | Gaudenti & Sons Corporation; Lic. No.: 283650-B | 231 VISTA DEL MAR REDONDO BEACH, CA 90277 |
| Engineer | Roth,, Jennifer Nicole; Lic. No.: C84889 | 110 THE VILLAGE UNIT 504 REDONDO BEACH, CA 90277 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/28/2021 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 2/28/2022 | Approved | DAVID TSAU |
| T-Bar Ceiling | 10/27/2022 | Approved | JOEY BUCHANAN |
| Green Building Rough | 11/29/2022 | Approved | JOEY BUCHANAN |
| Insulation | 1/13/2023 | Approved | JOEY BUCHANAN |
| Final | 1/27/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Green Building Final | 1/27/2023 | Not Ready for Inspection | AMANUEL BERHE |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Not Ready | AMANUEL BERHE |
| Smoke Detectors | 1/27/2023 | Approved | AMANUEL BERHE |
| Wood Frame | 1/27/2023 | Not Ready for Inspection | AMANUEL BERHE |
| Final | 2/2/2023 | Not Ready for Inspection | JOEY BUCHANAN |
| Green Building Final | 2/2/2023 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2023 | SGSOV Approved | JOEY BUCHANAN |
| Wood Frame | 2/2/2023 | Approved | JOEY BUCHANAN |
| Final | 3/14/2023 | Corrections Issued | AMANUEL BERHE |
| Final | 3/20/2023 | Conditional Approval | JOEY BUCHANAN |
| Final | 3/31/2026 | Permit Finaled | MICHAEL PETRUSKO |