6036-6038 W 75TH ST 90045

Certificate Information: 6036-6038 W 75TH ST 90045

Application / Permit
21016-10000-07725
Plan Check / Job No.
B21LA05636
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CHANGE PORTION OF STORAGE AREA TO JADU ( 492 SF), STORAGE ROOM. ADD WALLS TO SEPARATE GARAGE AREA, REBUILD REAR COVER PATIO, REMODEL KITCHEN, BATHROOM, CHANGE OUT SOME WINDOWS AND DOORS. JADU PER GCS-65852.2(e)(A) & 65852.22
Permit Issued
Issued on 2/10/2022
Issuing Office
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 SAM CHANG
Corrections Issued 5/4/2021 SAM CHANG
Quality Review Completed 5/5/2021 EUGENE BARBEAU
Building Plans Picked Up 5/6/2021 APPLICANT
Plan Check Approved 1/20/2022 SAM CHANG
Plan Check Approved 2/10/2022 SAM CHANG
Issued 2/10/2022 APPLICANT
CofO in Progress 8/26/2022 BOBBY KEY
Permit Finaled 8/31/2022 DANIEL ORRANTE
CofO Issued 8/31/2022 DANIEL ORRANTE
Permit Finaled 8/31/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/7/2021 CATHERINE ADROVER
Sewer availability Cleared 8/7/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 8/10/2021 CATHERINE ADROVER
Hydrant and Access approval Cleared 10/2/2021 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Dao,, Vinh Huu; Lic. No.: C78147 13191 DEAN ST      TUSTIN, CA 92780

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/15/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 3/15/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 3/15/2022 Approved BOBBY KEY
Green Building Rough 3/15/2022 Not Ready for Inspection BOBBY KEY
HVAC-Rough 3/15/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 3/15/2022 Partial Approval BOBBY KEY
Shower Pan 3/15/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 3/18/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/21/2022 Approved BOBBY KEY
HVAC-Rough 3/21/2022 Approved BOBBY KEY
Reinforced Concrete Frame 3/21/2022 Approved BOBBY KEY
Interior/Exterior Lathing 4/4/2022 Partial Approval RYAN SALAZAR
Wood Frame 4/4/2022 Partial Approval RYAN SALAZAR
Insulation 4/7/2022 Partial Approval BOBBY KEY
Drywall Nailing 4/12/2022 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 4/26/2022 Not Ready for Inspection BOBBY KEY
Wood Frame 4/26/2022 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 5/3/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 6/6/2022 Approved BOBBY KEY
PLUMBING-Final 6/6/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 6/7/2022 Conditional Approval BOBBY KEY
Gas Test 6/7/2022 Partial Approval BOBBY KEY
Green Building Rough 6/7/2022 Approved BOBBY KEY
HVAC-Rough 6/7/2022 Corrections Issued BOBBY KEY
Shower Pan 6/7/2022 Approved BOBBY KEY
ELECTRICAL-Final 6/23/2022 Corrections Issued BOBBY KEY
Final 6/23/2022 Corrections Issued BOBBY KEY
Green Building Final 6/23/2022 Partial Approval BOBBY KEY
HVAC-Final 6/23/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 6/23/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 6/23/2022 Partial Approval BOBBY KEY
ELECTRICAL-Final 6/29/2022 Partial Approval BOBBY KEY
Final 6/29/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 6/29/2022 Partial Approval BOBBY KEY
PLUMBING-Final 6/29/2022 Partial Approval BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Not Ready BOBBY KEY
Green Building Rough 7/5/2022 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 7/5/2022 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 7/5/2022 Not Ready for Inspection STEPHANIE SWANSON
Green Building Rough 7/7/2022 Approved BOBBY KEY
HVAC-Rough 7/7/2022 Approved BOBBY KEY
Interior/Exterior Lathing 7/7/2022 Partial Approval BOBBY KEY
Insulation 7/11/2022 Approved BOBBY KEY
Drywall Nailing 7/18/2022 Approved HERBERT GIRON
Interior/Exterior Lathing 7/25/2022 Approved ANDREW NAVE
Pre-Inspection 8/5/2022 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 8/10/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 8/23/2022 Approved BOBBY KEY
Final 8/23/2022 Corrections Issued BOBBY KEY
Green Building Final 8/23/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 8/23/2022 Approved BOBBY KEY
Final 8/26/2022 OK to Issue CofO BOBBY KEY