3758-3760 S TILDEN AVE 90034

Certificate Information: 3758-3760 S TILDEN AVE 90034

Application / Permit
21016-10000-07602
Plan Check / Job No.
B21LA05525
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING SFD WITH GARAGE TO SFD WITH ADU PER LAMC 12.22 A33 C & E
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 STARR CHEN
Corrections Issued 3/28/2021 STARR CHEN
Plan Check Approved 9/3/2021 DANIEL SANJUAN
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 9/24/2021 APPLICANT
CofO in Progress 6/9/2022 JOHNNY MIRANDA
Permit Finaled 6/30/2022 DANIEL ORRANTE
CofO Issued 6/30/2022 DANIEL ORRANTE
Permit Finaled 6/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/12/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 4/12/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 4/12/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 4/12/2021 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 5/18/2021 KIRK LINKLATER
Construction near power lines Cleared 6/26/2021 RIDWAN HARDY
Specific Plan Cleared 6/30/2021 EILEEN HUNT
Hydrant and Access approval Cleared 8/12/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2021 Approved JOHNNY MIRANDA
Underground Mechanical 12/3/2021 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 12/8/2021 Partial Approval OGANES TARAKHCHYAN
Wood Frame 12/14/2021 Partial Approval JOHNNY MIRANDA
Insulation 12/17/2021 Partial Approval JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 12/17/2021 Partial Approval JOHNNY MIRANDA
Insulation 12/20/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 12/22/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 12/22/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 12/22/2021 Approved JOHNNY MIRANDA
Drywall Nailing 12/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 1/3/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 1/3/2022 Partial Approval JOHNNY MIRANDA
Shower Pan 1/3/2022 Approved JOHNNY MIRANDA
Drywall Nailing 1/31/2022 Approved JOHNNY MIRANDA
HVAC-Rough 1/31/2022 Approved JOHNNY MIRANDA
Insulation 1/31/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 1/31/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 3/9/2022 Approved EVAN COOPER
ELECTRICAL-Final 3/9/2022 Approved EVAN COOPER
Final 3/9/2022 Corrections Issued EVAN COOPER
Green Building Final 3/9/2022 Approved EVAN COOPER
Green Building Rough 3/9/2022 Approved EVAN COOPER
HVAC-Final 3/9/2022 Approved EVAN COOPER
PLUMBING-Final 3/9/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/9/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 3/9/2022 Approved EVAN COOPER
Final 3/15/2022 Corrections Issued JOHNNY MIRANDA
Service/Power Release 6/8/2022 Approved JOHNNY MIRANDA
Final 6/9/2022 OK to Issue CofO JOHNNY MIRANDA