14320 W GILMORE ST 91401

Certificate Information: 14320 W GILMORE ST 91401

Application / Permit
21016-10000-07585
Plan Check / Job No.
B21LA05510
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Detached Garage conversion and addition to new ADU per Ordinance and LAMC 12.22 A33(c)&(d). All work per WFPP
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 ZAW HAN
Corrections Issued 4/7/2021 ZAW HAN
Plan Check Approved 4/27/2021 ZAW HAN
Issued 4/30/2021 APPLICANT
CofO in Progress 9/22/2022 RICHARD DOCKUS
CofO Issued 9/22/2022 MICHAEL SMITH
Permit Finaled 9/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/8/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/13/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/13/2021 ADRIAN CASTRO
Sewer availability Cleared 4/13/2021 ADRIAN CASTRO
"Q" conditions Cleared 4/14/2021 LAUREN PADICK
CPC Cleared 4/14/2021 LAUREN PADICK
Tenant Habitability Plan Cleared 4/21/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2021 Approved RICHARD DOCKUS
Footing/Foundation/Slab 8/30/2021 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 9/9/2021 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 9/21/2021 Approved RICHARD DOCKUS
Wood Frame 10/14/2021 Corrections Issued RICHARD DOCKUS
Wood Frame 10/21/2021 Partial Approval RICHARD DOCKUS
Interior/Exterior Lathing 12/1/2021 Partial Inspection WILLIAM KUEHN
Insulation 4/15/2022 Corrections Issued ALAN MORELOS
Drywall Nailing 4/21/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 4/21/2022 Approved ALAN MORELOS
Wood Frame 4/21/2022 Corrections Issued ALAN MORELOS
Final 6/24/2022 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 6/24/2022 Approved RICHARD DOCKUS
Wood Frame 6/24/2022 Approved RICHARD DOCKUS
Final 8/15/2022 Not Ready for Inspection RICHARD DOCKUS
Final 9/6/2022 Not Ready for Inspection RICHARD DOCKUS
Final 9/22/2022 OK to Issue CofO RICHARD DOCKUS