333 S BOYLSTON ST 90017
Certificate Information: 333 S BOYLSTON ST 90017
- Application / Permit
- 21016-10000-07575
- Plan Check / Job No.
- B21LA05487
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- STRUCTURAL ALTERATIONS ONLY. ADD (N) TRUSS AND REMOVE (E) COLUMNS. NO OTHER WORK UNDER THIS PERMIT.
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | JOE VO |
| Plans on Hold | 4/7/2021 | ALLEN MANALANSAN |
| Hold Released | 6/7/2021 | ALLEN MANALANSAN |
| Corrections Issued | 6/12/2021 | JOE VO |
| Quality Review Completed | 6/17/2021 | MICHAEL PEREZ |
| Disabled Access Plans Picked Up | 11/9/2021 | APPLICANT |
| Plan Check Approved | 11/18/2021 | JOE VO |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Permit Finaled | 1/4/2024 | KATY RAMIREZ |
Permit Application Clearance Information
| DAS Clearance | Cleared | 11/10/2021 | JOE VO |
Contact Information
| Contractor | C F P Construction Inc; Lic. No.: 700920-B | 426 CEDAR STREET LOS ANGELES, CA 90065 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/3/2021 | Approved | TIMOTHY BUXTON |
| Deputy Grading | 12/8/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Grading | 12/9/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Grading | 12/10/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Grading | 12/13/2021 | Conditional Approval | NICK DANERI |
| Deputy Grading | 12/17/2021 | Conditional Approval | JONATHAN QUACH |
| Piling/Pier/Caisson | 12/20/2021 | Partial Approval | TIMOTHY BUXTON |
| Piling/Pier/Caisson | 12/27/2021 | Partial Approval | TIMOTHY BUXTON |
| Pre-Inspection | 1/3/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Pre-Inspection | 1/4/2022 | Approved | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 1/10/2022 | Partial Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 1/18/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 1/18/2022 | Conditional Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 1/20/2022 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 1/25/2022 | Partial Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 1/25/2022 | Partial Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 1/27/2022 | Partial Approval | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 2/8/2022 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 2/16/2022 | Partial Approval | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 2/16/2022 | Partial Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 2/24/2022 | Conditional Approval | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 2/24/2022 | Partial Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/2/2022 | Conditional Approval | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 3/2/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Deputy Steel/Welding | 3/3/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/4/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/7/2022 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 3/8/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/9/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/10/2022 | Conditional Approval | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 3/10/2022 | Partial Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/11/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/14/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/16/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/18/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/21/2022 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Steel/Welding | 3/22/2022 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 3/30/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 4/26/2022 | Approved | RAFAEL ESPINOZA |
| Pre-Inspection | 6/8/2022 | Approved | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 6/15/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Fireproofing | 7/12/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Fireproofing | 7/13/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Drilled-In Anchors | 4/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Final | 4/24/2023 | Partial Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/24/2023 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 4/24/2023 | Approved | KATY RAMIREZ |
| Final | 5/1/2023 | Partial Inspection | KATY RAMIREZ |
| Special/Order Compliance | 5/11/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 1/3/2024 | Not Ready for Inspection | KATY RAMIREZ |