4647 N CARTWRIGHT AVE 91602
Certificate Information: 4647 N CARTWRIGHT AVE 91602
- Application / Permit
- 21016-10000-07482
- Plan Check / Job No.
- B21LA05438
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (18 x18) DETACHED GARAGE TO NEW ADU.
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | JESSE JIMENEZ |
| Corrections Issued | 3/25/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 6/2/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/28/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/28/2021 | JESSE ARELLANO |
| Plan Check Approved | 7/29/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 7/30/2021 | APPLICANT |
| Issued | 8/11/2021 | APPLICANT |
| CofO in Progress | 6/16/2022 | THOMAS FINNILA |
| CofO Issued | 8/15/2022 | MICHAEL SMITH |
| Permit Finaled | 8/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/26/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/19/2021 | MATTHEW CRAIG |
| Green Code | Cleared | 7/29/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Ross D Construction; Lic. No.: 871334-B | 22664 KITTRIDGE STREET WEST HILLS, CA 91307 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/18/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/9/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 9/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 9/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 9/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/12/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/12/2021 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 10/12/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 10/12/2021 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/21/2021 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/21/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 10/21/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/29/2021 | Approved | CALEB MEISTER |
| Deputy Drilled-In Anchors | 10/29/2021 | Approved | CALEB MEISTER |
| Deputy Wood Construction | 10/29/2021 | Approved | CALEB MEISTER |
| Green Building Rough | 10/29/2021 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 10/29/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 11/4/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 11/4/2021 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 11/23/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/14/2022 | Approved | DAVID MATSON |
| Final | 3/14/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 3/14/2022 | Approved | DAVID MATSON |
| Green Building Rough | 3/14/2022 | Approved | DAVID MATSON |
| MERV13>=Final | 3/14/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 3/14/2022 | Corrections Issued | DAVID MATSON |
| Final | 5/12/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 5/12/2022 | Conditional Approval | THOMAS FINNILA |
| Final | 6/15/2022 | OK to Issue CofO | THOMAS FINNILA |
| Smoke Detectors | 6/15/2022 | Approved | THOMAS FINNILA |