985 1/2 N DEXTER ST 90042
Certificate Information: 985 1/2 N DEXTER ST 90042
- Application / Permit
- 21016-10000-07368
- Plan Check / Job No.
- B21LA05340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EXISTING ATTACHED GARAGE AND WORKSHOP CONVERTING INTO AN ATTACHED ADU TO (E) DUPLEX.
- Permit Issued
- Issued on 11/9/2021
- Issuing Office
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | TSE MING HUANG |
| Corrections Issued | 3/25/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 8/21/2021 | DANIEL SANJUAN |
| Plan Check Approved | 9/29/2021 | FERNANDO FLORES |
| Issued | 11/9/2021 | APPLICANT |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| CofO in Progress | 8/31/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/17/2021 | CELINA MORENO |
| Sewer availability | Cleared | 9/17/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Montiel,, Rudolf Celestino; Lic. No.: C84972 | 7100 WESTWIND DR STE 250 EL PASO, TX 79912 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/8/2021 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/13/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/17/2021 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/17/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 12/22/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/20/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/29/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/19/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/19/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 8/23/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/23/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 8/31/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 9/8/2022 | Approved | HAMIK HARTOUNIAN |