241 E 80TH ST 90003
Certificate Information: 241 E 80TH ST 90003
- Application / Permit
- 21016-10000-07348
- Plan Check / Job No.
- B21LA05328
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE/RECREATION ROOM INTO ADU Per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 10/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | RAHEL BEYENE |
| Corrections Issued | 3/27/2021 | RAHEL BEYENE |
| Plan Check Approved | 3/2/2022 | KHUONG TRUONG |
| Issued | 3/11/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 9/15/2022 | LILIANA PORTILLO |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
| CofO Issued | 10/1/2022 | DEROLD HAUFF |
| Permit Finaled | 10/1/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/16/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 11/30/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/29/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Approved | JUSTIN CURTIS |
| Footing/Foundation/Slab | 4/1/2022 | Approved | JUSTIN CURTIS |
| Sewer | 4/1/2022 | Approved | JUSTIN CURTIS |
| BUILDING-Rough-Frame | 4/19/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/19/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 4/19/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/19/2022 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 4/19/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/20/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 4/20/2022 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 4/22/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/25/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Approved | LILIANA PORTILLO |
| Insulation | 4/27/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/29/2022 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 5/3/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/3/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/16/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 6/16/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 6/16/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 6/16/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 6/16/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 6/16/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/29/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 6/29/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 6/29/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 6/29/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 6/29/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 6/29/2022 | Approved | LILIANA PORTILLO |
| Final | 9/7/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 9/7/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/14/2022 | Approved | LILIANA PORTILLO |
| Final | 9/14/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 9/19/2022 | Approved | LILIANA PORTILLO |