241 E 80TH ST 90003

Certificate Information: 241 E 80TH ST 90003

Application / Permit
21016-10000-07348
Plan Check / Job No.
B21LA05328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE/RECREATION ROOM INTO ADU Per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/11/2022
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RAHEL BEYENE
Corrections Issued 3/27/2021 RAHEL BEYENE
Plan Check Approved 3/2/2022 KHUONG TRUONG
Issued 3/11/2022 APPLICANT
Building Plans Picked Up 3/16/2022 APPLICANT
CofO in Progress 9/15/2022 LILIANA PORTILLO
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/16/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/16/2021 CECILIO NAVARRO
Sewer availability Cleared 6/16/2021 CECILIO NAVARRO
Construction near power lines Cleared 11/30/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/29/2022 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 4/1/2022 Approved JUSTIN CURTIS
Footing/Foundation/Slab 4/1/2022 Approved JUSTIN CURTIS
Sewer 4/1/2022 Approved JUSTIN CURTIS
BUILDING-Rough-Frame 4/19/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 4/19/2022 Approved LILIANA PORTILLO
HVAC-Rough 4/19/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 4/19/2022 Corrections Issued LILIANA PORTILLO
Underground Mechanical 4/19/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 4/20/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/20/2022 Approved LILIANA PORTILLO
Underground Mechanical 4/20/2022 Approved LILIANA PORTILLO
Deputy Wood Construction 4/22/2022 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/25/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/25/2022 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 4/27/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Approved LILIANA PORTILLO
Insulation 4/27/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/29/2022 Partial Approval HORACE FULTZ
Drywall Nailing 5/3/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/3/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/16/2022 Corrections Issued LILIANA PORTILLO
Final 6/16/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 6/16/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 6/16/2022 Approved LILIANA PORTILLO
PLUMBING-Final 6/16/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 6/16/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 6/29/2022 Corrections Issued LILIANA PORTILLO
Final 6/29/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 6/29/2022 Approved LILIANA PORTILLO
HVAC-Final 6/29/2022 Approved LILIANA PORTILLO
PLUMBING-Final 6/29/2022 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/29/2022 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 6/29/2022 Approved LILIANA PORTILLO
Final 9/7/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 9/7/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 9/14/2022 Approved LILIANA PORTILLO
Final 9/14/2022 OK to Issue CofO LILIANA PORTILLO
Service/Power Release 9/19/2022 Approved LILIANA PORTILLO