19803 W RINALDI ST 91326
Certificate Information: 19803 W RINALDI ST 91326
- Application / Permit
- 21016-10000-07299
- Plan Check / Job No.
- B21LA05276
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TI-REMODEL OF EXISTING RETAIL SPACE. NO CHANGE IN USE, SQFT, SITE, TENANT OR STOREFRONT. 3993 SQFT ALL INTERIOR. REPLACEMENT OF ONE RTU. INCL: PARTITIONS, DOORS, CEILING, BATHROOM, ECT. MINOR MEP WORK. BOTH SHELVING UNDER SEPARATE PERMIT.
- Permit Issued
- Issued on 6/9/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/25/2021
Permit Application Status History
| Submitted | 3/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 3/28/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 4/28/2021 | ADAM HEGAZI |
| Issued | 6/9/2021 | APPLICANT |
| Building Plans Picked Up | 6/11/2021 | APPLICANT |
| Permit Finaled | 10/25/2021 | JEFFREY FULTON |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/31/2021 | KORA MCNAUGHTON |
| "D" conditions | Cleared | 4/14/2021 | LAUREN PADICK |
| ZA Case | Cleared | 4/14/2021 | LAUREN PADICK |
| ZA Case | Cleared | 4/14/2021 | LAUREN PADICK |
| ZA Case | Cleared | 4/14/2021 | LAUREN PADICK |
Contact Information
| Contractor | Lakeview Construction Inc; Lic. No.: 671201-B | 10505 CORPORATE DRIVE STE 200 PLEASANT PRAIRIE, WI 53158 |
| Engineer | Nemeth,, David L; Lic. No.: C71921 | 3030 W STREETSBORO RD RICHFIELD, OH 44202 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/29/2021 | No Access for Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 8/2/2021 | Conditional Approval | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 8/3/2021 | Conditional Approval | JEFFREY FULTON |
| Light Gage Steel Frame | 8/5/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 8/9/2021 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 8/20/2021 | Not Ready for Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 10/4/2021 | Partial Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 10/13/2021 | Approved | JEFFREY FULTON |
| Final | 10/15/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 10/15/2021 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/15/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 10/15/2021 | Approved | JEFFREY FULTON |
| Final | 10/25/2021 | Permit Finaled | JEFFREY FULTON |
| Green Building Final | 10/25/2021 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Approved | JEFFREY FULTON |