17640 W LEMAY PL 91406

Certificate Information: 17640 W LEMAY PL 91406

Application / Permit
21016-10000-07094
Plan Check / Job No.
B21LA05145
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. Garage conversion to accessory dwelling unit and small addition per ordinance
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
Issued on 7/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/23/2021 MONICA RAMIREZ
Corrections Issued 3/24/2021 MONICA RAMIREZ
Applicant returned to address corrections 4/29/2021 MONICA RAMIREZ
Plan Check Approved 6/15/2021 MONICA RAMIREZ
Issued 7/1/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/5/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 4/5/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/6/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/8/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 6/12/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/15/2021 Approved SEAN HAUPT
Footing/Foundation/Slab 10/25/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/19/2021 Approved SEAN HAUPT
ELECTRICAL-Rough 11/19/2021 Approved SEAN HAUPT
Gas Test 11/19/2021 Partial Approval SEAN HAUPT
Green Building Rough 11/19/2021 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 11/19/2021 Approved SEAN HAUPT
Insulation 12/1/2021 Approved SEAN HAUPT
Interior/Exterior Lathing 12/1/2021 Approved SEAN HAUPT
Shower Pan 12/1/2021 Approved SEAN HAUPT
Drywall Nailing 12/6/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/23/2022 Approved SEAN HAUPT
ELECTRICAL-Final 3/23/2022 Approved SEAN HAUPT
Final 3/23/2022 Corrections Issued SEAN HAUPT
Green Building Final 3/23/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 3/23/2022 Approved SEAN HAUPT
HVAC-Final 3/23/2022 Approved SEAN HAUPT
PLUMBING-Final 3/23/2022 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 3/23/2022 Approved SEAN HAUPT