12835 N ENCINITAS AVE 91342
Certificate Information: 12835 N ENCINITAS AVE 91342
- Application / Permit
- 21016-10000-07017
- Plan Check / Job No.
- B21LA05115
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- CHANGE OF OCCUPANCY FROM R-1 (TRANSIENT HOTEL) AND APARTMENT TO R-2 (NON-TRANSIENT HOTEL) AND APARTMENT. ACCESSIBILITY UPGRADES. PROJECT HOMEKEY.
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Current Status
- CofO Issued on 1/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | KEVIN MORALES |
| Corrections Issued | 3/30/2021 | KEVIN MORALES |
| Quality Review Completed | 3/31/2021 | EUGENE BARBEAU |
| Plan Check Approved | 7/19/2021 | KEVIN MORALES |
| Issued | 7/20/2021 | APPLICANT |
| Building Plans Picked Up | 7/26/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 7/26/2021 | APPLICANT |
| CofO in Progress | 12/7/2022 | ANDREW DORSO |
| CofO Issued | 1/17/2023 | JEFFREY DURAN |
| Permit Finaled | 1/17/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/7/2021 | GUILLERMO PETRA |
| ZA Case | Cleared | 5/14/2021 | MARITZA PRZEKOP |
| ZA Case | Cleared | 5/14/2021 | MARITZA PRZEKOP |
| ZA Case | Cleared | 5/18/2021 | MATTHEW LUM |
| Fire Marshal Fire Life Safety | Cleared | 6/9/2021 | MENOA AGHAJANI |
| DAS Clearance | Cleared | 6/18/2021 | EUGENE BARBEAU |
Contact Information
| Architect | Geronaga,, Rhodore Candelaria; Lic. No.: C24750 | 7267 EAST DRAKE DRIVE ANAHEIM HILLS, CA 92807 |
| Contractor | Belfor Usa Group Inc; Lic. No.: 810553-B | 185 OAKLAND AVENUE STE 150 BIRMINGHAM, MI 48009 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 7/29/2021 | Partial Inspection | ANDREW DORSO |
| Pre-Inspection | 7/29/2021 | Corrections Issued | ANDREW DORSO |
| Pre-Inspection | 8/2/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 8/25/2021 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 8/27/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 9/2/2021 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Approved | ANDREW DORSO |
| Footing/Foundation/Slab | 9/10/2021 | Approved | ANDREW DORSO |
| Insulation | 9/10/2021 | Approved | ANDREW DORSO |
| Wood Frame | 9/10/2021 | Approved | ANDREW DORSO |
| Deputy Reinf. Concrete | 9/14/2021 | Conditional Approval | JEFFREY DURAN |
| Deputy Wood Construction | 9/20/2021 | Conditional Approval | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2021 | Partial Approval | ANDREW DORSO |
| Deputy Wood Construction | 9/21/2021 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 10/7/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 10/29/2021 | Approved | ANDREW DORSO |
| Final | 1/5/2022 | Partial Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 1/5/2022 | Not Ready for Inspection | ANDREW DORSO |
| Pre-Inspection | 2/16/2022 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 2/22/2022 | Approved | ANDREW DORSO |
| Insulation | 2/22/2022 | Approved | ANDREW DORSO |
| Final | 4/26/2022 | Partial Inspection | KENNETH ROBERTS |
| Smoke Detectors | 4/26/2022 | Approved | KENNETH ROBERTS |
| Final | 12/1/2022 | OK to Issue CofO | ANDREW DORSO |
| Special/Order Compliance | 12/1/2022 | Partial Inspection | DEANDRE HOFFMAN |