6065 1/2 W SELMA AVE 90028

Certificate Information: 6065 1/2 W SELMA AVE 90028

Application / Permit
21016-10000-06915
Plan Check / Job No.
B21LA05053
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: Converting the existing Type V garage into an ADU per GCS 65852.2(e)(1)(A)., while making no changes to the building's footprint. Removing the existing door and windows and installing a new door, and window. Installing new Building non load-bearing walls to create a bathroom, kitchenette with all electric appliances, indoor closet, and outdoor closet. The new bathroom contains a shower, toilet, and sink. The kitchenette contains a sink, garbage disposal, and electric cooktop. The property's existing 4" sewer line and water service is to be extended to accommodate the new bathroom and kitchenette. Installing an electric meter and electric water heater. Installing lighting fixtures, and electrical outlets. Installing new ridge beam and two new posts then vaulting the ceiling.
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 3/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/22/2021 ZAW HAN
Corrections Issued 3/22/2021 ZAW HAN
Plan Check Approved 5/5/2021 ZAW HAN
Issued 7/1/2021 APPLICANT
CofO in Progress 4/7/2022 BRIAN SULLIVAN
No Progress 3/22/2023 RUBEN SALAS
CofO in Progress 3/28/2023 RUBEN SALAS
Permit Finaled 3/28/2023 DEROLD HAUFF
CofO Issued 3/28/2023 DEROLD HAUFF
Permit Finaled 3/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/1/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 4/1/2021 CELINA MORENO
Sewer availability Cleared 4/1/2021 CELINA MORENO
City Hist. Cultural Monument Cleared 4/5/2021 MICAELA TORRES-GIL
Historic monument Cleared 4/5/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 4/16/2021 GRACIELA ACOSTA
"Q" conditions Cleared 4/22/2021 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 4/29/2021 CELINA MORENO

Contact Information

Contractor Brauner Construction & Realty; Lic. No.: 1051764-B 3734 S CANFIELD AVE APT 228      LOS ANGELES, CA 90034

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/27/2022 Approved BRIAN SULLIVAN
Insulation 1/27/2022 Approved BRIAN SULLIVAN
Special/Order Compliance 1/27/2022 Corrections Issued BRIAN SULLIVAN
Wood Frame 1/27/2022 Approved BRIAN SULLIVAN
Drywall Nailing 2/4/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 2/4/2022 Approved BRIAN SULLIVAN
Shower Pan 2/4/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 3/18/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 3/18/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 3/18/2022 Corrections Issued BRIAN SULLIVAN
Green Building Final 3/18/2022 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 3/18/2022 Approved BRIAN SULLIVAN
HVAC-Final 3/18/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 3/18/2022 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/18/2022 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 3/18/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 3/29/2022 Approved ARTHUR SARGSYAN
Final 3/29/2022 Conditional Approval ARTHUR SARGSYAN
Green Building Final 3/29/2022 Approved ARTHUR SARGSYAN
HVAC-Final 3/29/2022 Approved ARTHUR SARGSYAN
PLUMBING-Final 3/29/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/29/2022 SGSOV Approved ARTHUR SARGSYAN
ELECTRICAL-Final 4/4/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 4/4/2022 Corrections Issued BRIAN SULLIVAN
PLUMBING-Final 4/4/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 4/6/2022 Approved BRIAN SULLIVAN
Final 4/6/2022 OK to Issue CofO BRIAN SULLIVAN
HVAC-Final 4/6/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 4/6/2022 Approved BRIAN SULLIVAN
Special/Order Compliance 3/22/2023 Corrections Issued RUBEN SALAS