2205 N DALY ST 1-6 90031

Certificate Information: 2205 N DALY ST 1-6 90031

Application / Permit
21016-10000-06846
Plan Check / Job No.
B21LA04993
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ALTERATION TO 2-STORY, TYPE V, 60 X 70 5-UNIT APT HOUSE: CONVERT 1ST FLOOR [18 X 27] PORTION OF PARKING AREA TO ADU PER CITY PLANNING ADM -2021-6794-ADU. CHANGE PARKING LAYOUT.
Permit Issued
Issued on 3/27/2022
Issuing Office
Current Status
CofO Issued on 1/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/22/2021 JESSE JIMENEZ
Corrections Issued 3/24/2021 JESSE JIMENEZ
Applicant returned to address corrections 9/5/2021 DANIEL SANJUAN
Applicant returned to address corrections 10/15/2021 ZAW HAN
Plan Check Approved 10/18/2021 ZAW HAN
Issued 3/27/2022 APPLICANT
Building Plans Picked Up 10/26/2022 APPLICANT
CofO in Progress 1/9/2024 RAMAZANALI ALMASI
CofO Issued 1/10/2024 ERNESTO CORRAL
Permit Finaled 1/10/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 4/29/2021 JEANIE LAM
HPOZ Cleared 8/10/2021 JONATHAN KAPLAN
Eng Process Fee Ord 176,300 Cleared 8/20/2021 CECILIO NAVARRO
Sewer availability Cleared 10/1/2021 CECILIO NAVARRO

Contact Information

Contractor Ariel Muller; Lic. No.: 1026822-B 525 N FULLER AVE      LOS ANGELES, CA 90036
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/16/2022 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 6/28/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 6/28/2022 Partial Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Inspection JULIAN CAPUCETTI
Wood Frame 5/16/2023 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 5/23/2023 Approved JULIAN CAPUCETTI
Insulation 5/31/2023 Partial Approval JULIAN CAPUCETTI
Interior/Exterior Lathing 5/31/2023 Approved JULIAN CAPUCETTI
Insulation 6/2/2023 Approved RONALD JIMENEZ
Drywall Nailing 6/13/2023 Approved JULIAN CAPUCETTI
Interior/Exterior Lathing 7/14/2023 Not Ready for Inspection JULIAN CAPUCETTI
Interior/Exterior Lathing 7/18/2023 Approved JULIAN CAPUCETTI
Interior/Exterior Lathing 7/19/2023 Approved JULIAN CAPUCETTI
Final 12/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 12/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/19/2023 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 12/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 12/26/2023 No Access for Inspection RAFAEL CORTES
Green Building Final 12/26/2023 No Access for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 12/26/2023 No Access for Inspection RAFAEL CORTES
Final 1/3/2024 Partial Inspection RAMAZANALI ALMASI
Green Building Final 1/3/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 1/3/2024 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 1/3/2024 Approved RAMAZANALI ALMASI
Final 1/9/2024 OK to Issue CofO RAMAZANALI ALMASI
Green Building Final 1/9/2024 Approved RAMAZANALI ALMASI