742-744 W 115TH ST 90044

Certificate Information: 742-744 W 115TH ST 90044

Application / Permit
21016-10000-06839
Plan Check / Job No.
B21LA04988
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED TO CONVERT (E) ATTACHED GARAGE OF 402 SQ FT TO AN ACCESSORY DWELLING UNIT (ADU) Per GCS 65852.2(e)(1)((A)
Permit Issued
Issued on 6/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2021 APPLICANT
Assigned to Plan Check Engineer 7/13/2021 JOSEPH RAFOLS
Corrections Issued 7/13/2021 JOSEPH RAFOLS
Applicant returned to address corrections 12/29/2021 KHUONG TRUONG
Applicant returned to address corrections 1/27/2022 KHUONG TRUONG
Plan Check Approved 2/23/2022 KHUONG TRUONG
Building Plans Picked Up 3/2/2022 APPLICANT
Issued 6/9/2022 APPLICANT
CofO in Progress 2/28/2023 JAMES CHAVEZ
CofO Issued 2/28/2023 ANSON MAGLASANG
Permit Finaled 2/28/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/23/2021 JEANETTE VONG
Sewer availability Cleared 11/23/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 12/10/2021 KHOUNG LE

Contact Information

Contractor R P A Construction Planning Services; Lic. No.: 1089863-B 611 N LOS ROBLES AVE APT #4      PASADENA, CA 91101
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 7/13/2022 Approved JOHN KLARIN
PLUMBING-Rough 7/13/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 8/2/2022 Corrections Issued JOHN KLARIN
PLUMBING-Rough 8/2/2022 Corrections Issued JOHN KLARIN
Wood Frame 8/2/2022 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 8/17/2022 Approved JOHN KLARIN
ELECTRICAL-Rough 8/17/2022 Approved JOHN KLARIN
Green Building Rough 8/17/2022 Approved JOHN KLARIN
MERV13>=Rough 8/17/2022 Approved JOHN KLARIN
PLUMBING-Rough 8/17/2022 Partial Approval JOHN KLARIN
Insulation 9/12/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 9/12/2022 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 10/6/2022 Approved ALIZAH MAYAGOITIA
Final 11/29/2022 Corrections Issued JOHN KLARIN
Green Building Final 11/29/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Final 11/29/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 11/29/2022 Not Ready for Inspection JOHN KLARIN
Final 1/30/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 1/30/2023 Corrections Issued JAMES CHAVEZ
Smoke Detectors 1/30/2023 Corrections Issued JAMES CHAVEZ
Final 2/10/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 2/10/2023 Approved JAMES CHAVEZ
Smoke Detectors 2/10/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 2/27/2023 Approved JAMES CHAVEZ
Final 2/27/2023 OK to Issue CofO JAMES CHAVEZ
HVAC-Final 2/27/2023 Approved JAMES CHAVEZ
PLUMBING-Final 2/27/2023 Approved JAMES CHAVEZ