20445 W SHERMAN WAY 91306
Certificate Information: 20445 W SHERMAN WAY 91306
- Application / Permit
- 21016-10000-06833
- Plan Check / Job No.
- B21LA04973
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Tenant improvement to an existing commercial building for a new restaurant use (Habit Burger Grill).
- Permit Issued
- Issued on 8/5/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2021
Permit Application Status History
| Submitted | 3/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | JOE VO |
| Corrections Issued | 3/20/2021 | JOE VO |
| Quality Review Completed | 3/22/2021 | LARRY LEE |
| Green Plans Picked Up | 4/28/2021 | APPLICANT |
| Applicant returned to address corrections | 5/11/2021 | JOE VO |
| Applicant returned to address corrections | 6/24/2021 | JOE VO |
| Plan Check Approved | 8/3/2021 | JOE VO |
| Issued | 8/5/2021 | APPLICANT |
| Permit Finaled | 12/1/2021 | DANIEL MC AULIFFE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/24/2021 | GABRIEL ROBLES |
| "Q" conditions | Cleared | 3/26/2021 | MAXFIELD VERMY |
| Food Service Establishment | Cleared | 6/11/2021 | RAMESHBHAIR PATEL |
| Food establishment approval | Cleared | 6/14/2021 | LACDHS APPROVED |
| Green Code | Cleared | 7/9/2021 | MICHAEL PEREZ |
| DAS Clearance | Cleared | 7/13/2021 | MICHAEL PEREZ |
Contact Information
| Architect | Lingle,, Carl Lee; Lic. No.: C29985 | 9113 IL 73 NORTH WINSLOW, IL 61089 |
| Contractor | Mitchell General Contractors Inc; Lic. No.: 831334-B | 52 TESLA IRVINE, CA 92618 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/20/2021 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 8/20/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 8/20/2021 | Corrections Issued | ANDREW DORSO |
| Deputy Drilled-In Anchors | 8/23/2021 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 8/27/2021 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 9/1/2021 | Corrections Issued | DANIEL VARNUM |
| Light Gage Steel Frame | 9/8/2021 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 9/10/2021 | Partial Approval | DANIEL VARNUM |
| Insulation | 9/14/2021 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 9/16/2021 | Approved | DANIEL VARNUM |
| Wood Frame | 9/16/2021 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 9/23/2021 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/6/2021 | Approved | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/12/2021 | Partial Inspection | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 11/4/2021 | Approved | DANIEL VARNUM |
| T-Bar Ceiling | 11/8/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| T-Bar Ceiling | 11/10/2021 | Approved | ALAN NOVAK |
| Footing/Foundation/Slab | 11/12/2021 | Partial Approval | ALAN NOVAK |
| Final | 11/30/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 11/30/2021 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 11/30/2021 | Approved | JEFFREY FULTON |
| Final | 12/1/2021 | Permit Finaled | DANIEL MC AULIFFE |
| Green Building Final | 12/1/2021 | Approved | DANIEL MC AULIFFE |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Approved | DANIEL MC AULIFFE |