Pre-Inspection
|
5/5/2021
|
Approved
|
ANDREW DORSO
|
|
Deputy Drilled-In Anchors
|
5/10/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Excavation/Setback/Form/Re-Bar
|
5/11/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Other (see comments)
|
5/13/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Other (see comments)
|
5/14/2021
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Drilled-In Anchors
|
5/18/2021
|
Approved
|
HAMID PISHEHVAR
|
|
Deputy Reinf. Concrete
|
5/21/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Other (see comments)
|
5/27/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
6/1/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
6/1/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
6/2/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
6/2/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
6/3/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
6/4/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
6/7/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
6/8/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/9/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
6/9/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
6/10/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
6/11/2021
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/15/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
6/16/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
6/17/2021
|
No Access for Inspection
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
6/18/2021
|
Partial Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
6/21/2021
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Masonry
|
6/23/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Masonry
|
6/25/2021
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
7/6/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
7/9/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
7/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
7/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
7/16/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
7/21/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Pre-Inspection
|
7/22/2021
|
Partial Inspection
|
DANIEL VARNUM
|
|
Wall Anchors
|
7/22/2021
|
No Access for Inspection
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
7/23/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
7/26/2021
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Reinf. Concrete
|
7/27/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
7/27/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
7/29/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
8/3/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Other (see comments)
|
8/10/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Other (see comments)
|
8/19/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
8/24/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
9/14/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
9/15/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
9/15/2021
|
No Result Entered
|
GARY EWELL
|
|
Deputy Drilled-In Anchors
|
9/16/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
9/20/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
9/28/2021
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
10/5/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
10/7/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Reinf. Concrete
|
10/12/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Reinf. Concrete
|
10/13/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
10/14/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
10/14/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
10/19/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
10/21/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
10/29/2021
|
Conditional Approval
|
KENNETH ROBERTS
|
|
Deputy Reinf. Concrete
|
11/5/2021
|
Conditional Approval
|
JEFFREY FULTON
|
|
Deputy Drilled-In Anchors
|
12/14/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
12/14/2021
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
12/15/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
12/15/2021
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
12/16/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
12/16/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
12/17/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
12/17/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
12/20/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
12/20/2021
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
1/11/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
1/11/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Drilled-In Anchors
|
1/12/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
1/12/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
1/13/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
1/13/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
1/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
1/14/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
1/18/2022
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Steel/Welding
|
1/18/2022
|
Conditional Approval
|
PAUL DAVIDSON
|
|
Deputy Drilled-In Anchors
|
1/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
1/25/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Drilled-In Anchors
|
1/26/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
1/26/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
1/27/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
1/27/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
1/28/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
1/28/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Drilled-In Anchors
|
1/31/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
1/31/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
2/8/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
2/9/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
2/10/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
2/11/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Steel/Welding
|
2/14/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
2/23/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
2/24/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
2/25/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
2/28/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Steel/Welding
|
2/28/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
3/1/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
3/1/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
3/2/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
3/3/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Steel/Welding
|
3/3/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
3/4/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
3/7/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Deputy Reinf. Concrete
|
3/7/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
3/8/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
3/11/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
3/14/2022
|
Conditional Approval
|
DANIEL VARNUM
|
|
Deputy Reinf. Concrete
|
3/15/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
3/16/2022
|
Conditional Approval
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
3/17/2022
|
Conditional Approval
|
CAMERON CHABAN
|
|
Final
|
4/12/2022
|
Partial Inspection
|
ANDREW DORSO
|
|
SGSOV-Seismic Gas S/O Valve
|
4/12/2022
|
SGSOV Approved
|
ANDREW DORSO
|
|
Smoke Detectors
|
4/12/2022
|
Not Ready for Inspection
|
ANDREW DORSO
|
|
Final
|
5/6/2022
|
Permit Finaled
|
ANDREW DORSO
|
|
Smoke Detectors
|
5/6/2022
|
Approved
|
ANDREW DORSO
|