10627 W OHIO AVE 90024

Certificate Information: 10627 W OHIO AVE 90024

Application / Permit
21016-10000-06773
Plan Check / Job No.
B21LA04927
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTERIOR REMODEL TO ADD NEW WINDOWS AND DOORS AND INTERIOR REMODEL TO CHANGE FLOOR LAY OUT ON 1ST AND 2ND FLOORS OF AN (E) SINGLE FAMILY DWELLING AND ADD NEW STAIRS (see comments)
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
Permit Finaled on 1/3/2023

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 MINA HABIB
Corrections Issued 4/14/2021 MINA HABIB
Quality Review Completed 4/16/2021 FARUK SEZER
Applicant returned to address corrections 7/29/2021 MINA HABIB
Applicant returned to address corrections 7/30/2021 MINA HABIB
Applicant returned to address corrections 8/19/2021 MINA HABIB
Applicant returned to address corrections 8/25/2021 MINA HABIB
Applicant returned to address corrections 11/1/2021 MINA HABIB
Applicant returned to address corrections 11/18/2021 MINA HABIB
Applicant returned to address corrections 12/8/2021 MINA HABIB
Applicant returned to address corrections 12/9/2021 MINA HABIB
Applicant returned to address corrections 12/29/2021 MINA HABIB
Plan Check Approved 1/6/2022 MINA HABIB
Issued 1/13/2022 APPLICANT
Building Plans Picked Up 1/19/2022 APPLICANT
Permit Finaled 1/3/2023 ASHLEY THOMPSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/6/2022 MINA HABIB

Contact Information

Contractor Owner-Builder       ,
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2022 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/25/2022 Approved OGANES TARAKHCHYAN
Wood Frame 2/1/2022 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 4/6/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 5/2/2022 Approved OGANES TARAKHCHYAN
Insulation 5/5/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/12/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/17/2022 Approved OGANES TARAKHCHYAN
Wood Frame 6/22/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/27/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/28/2022 Approved OGANES TARAKHCHYAN
Insulation 7/15/2022 Approved OGANES TARAKHCHYAN
Shower Pan 7/15/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/21/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 7/27/2022 Partial Inspection JOHN KIDWELL
HVAC-Final 11/3/2022 Conditional Approval ASHLEY THOMPSON
HVAC-Final 12/13/2022 Approved ASHLEY THOMPSON
PLUMBING-Final 12/13/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 12/28/2022 Corrections Issued ASHLEY THOMPSON
Final 12/28/2022 Not Ready for Inspection ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 12/28/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 12/29/2022 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 12/30/2022 Approved OGANES TARAKHCHYAN
Final 1/3/2023 Permit Finaled ASHLEY THOMPSON