4648 1/2 N VERDUGO ROAD 90065

Certificate Information: 4648 1/2 N VERDUGO ROAD 90065

Application / Permit
21016-10000-06721
Plan Check / Job No.
B21LA04887
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)(d)(g) PER WFPP
Permit Issued
Issued on 3/29/2023
Issuing Office
Metro
Current Status
Issued on 3/29/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/22/2021 JESSE JIMENEZ
Corrections Issued 3/23/2021 JESSE JIMENEZ
Building Plans Picked Up 3/30/2021 APPLICANT
Application Withdrawn 8/15/2022 KHUONG TRUONG
No Progress 2/27/2023 CHRISTOPHER KOMANCHECK
Re-Activate Applicaton 2/27/2023 CHRISTOPHER KOMANCHECK
Plan Check Approved 2/27/2023 FERNANDO FLORES
Issued 3/29/2023 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 4/25/2022 RIDWAN HARDY
Address approval Cleared 5/14/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/3/2022 JEANETTE VONG
Sewer availability Cleared 8/3/2022 JEANETTE VONG
Supp. Use District POD/CDO/TDO Cleared 8/18/2022 NASHYA JENSEN

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B 3401 OCEAN VIEW BLVD      GLENDALE, CA 91208

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/16/2023 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 9/1/2023 Corrections Issued CRAIG VAUGHAN
Pre-Inspection 10/16/2023 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 10/30/2023 Approved CRAIG VAUGHAN
Green Building Rough 8/20/2024 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 8/20/2024 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 8/20/2024 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 9/20/2024 Approved ROY SPAULDING
Verify Sprinkler Sign Off 9/20/2024 Approved ROY SPAULDING
Wood Frame 9/20/2024 Approved ROY SPAULDING
Insulation 10/8/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 10/8/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 10/16/2024 Approved ROY SPAULDING
Final 3/10/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 3/10/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 3/10/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/10/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Smoke Detectors 3/10/2025 Approved ALIZAH MAYAGOITIA
Final 3/18/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 3/18/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready ALIZAH MAYAGOITIA
Final 3/24/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 3/24/2025 Not Ready for Inspection DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 3/24/2025 SGSOV Not Ready DAVID WILLIAMS
Final 4/14/2025 Corrections Issued LILIANA PORTILLO
Green Building Final 4/14/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/14/2025 SGSOV Approved LILIANA PORTILLO
Final 4/21/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 4/21/2025 Not Ready for Inspection DAVID WILLIAMS
Final 5/8/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Final 5/8/2025 Not Ready for Inspection DAVID WILLIAMS
Final 6/10/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Final 6/10/2025 Approved DAVID WILLIAMS
Final 8/29/2025 Corrections Issued DAVID WILLIAMS
Final 10/16/2025 Corrections Issued RONNIE MEDINA
Final 1/15/2026 Not Ready for Inspection RONNIE MEDINA
Final 2/27/2026 Corrections Issued LILIANA PORTILLO
Final 5/22/2026 Corrections Issued ROY SPAULDING
Final 7/20/2026 Corrections Issued LILIANA PORTILLO