363 1/2 N CHICAGO ST 90033

Certificate Information: 363 1/2 N CHICAGO ST 90033

Application / Permit
21016-10000-06694
Plan Check / Job No.
B21LA04871
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) THREE-CAR GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 11/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/17/2021 FARSHAD ALIMOHAMADI
Corrections Issued 3/18/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 5/13/2021 FERNANDO FLORES
Plan Check Approved 9/21/2021 SINA KHOSRAVI
Issued 10/20/2021 APPLICANT
Building Plans Picked Up 10/21/2021 APPLICANT
CofO in Progress 11/3/2022 OSVALDO PARAMO
CofO in Progress 11/3/2022 OSVALDO PARAMO
Permit Finaled 11/9/2022 DEROLD HAUFF
CofO Issued 11/9/2022 DEROLD HAUFF
Permit Finaled 11/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/7/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 4/7/2021 JEANIE LAM
Sewer availability Cleared 4/7/2021 JEANIE LAM
Grading Pre-Inspection Cleared 4/26/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/25/2022 Approved SHAVONNE ESPINOZA
Pre-Inspection 2/1/2022 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/11/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 3/3/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 3/8/2022 Approved OSVALDO PARAMO
HVAC-Rough 3/8/2022 Approved OSVALDO PARAMO
Deputy Wood Construction 3/16/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/17/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 3/17/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/23/2022 Partial Approval OSVALDO PARAMO
Insulation 3/30/2022 Approved OSVALDO PARAMO
Drywall Nailing 4/5/2022 Approved OSVALDO PARAMO
Final 7/25/2022 Corrections Issued CRAIG VAUGHAN
Pool Piping 7/25/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 7/25/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 8/18/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 8/18/2022 Not Ready for Inspection OSVALDO PARAMO
Final 10/20/2022 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 10/20/2022 Not Ready for Inspection OSVALDO PARAMO
Final 11/2/2022 OK to Issue CofO OSVALDO PARAMO
Smoke Detectors 11/2/2022 Approved OSVALDO PARAMO