363 1/2 N CHICAGO ST 90033
Certificate Information: 363 1/2 N CHICAGO ST 90033
- Application / Permit
- 21016-10000-06694
- Plan Check / Job No.
- B21LA04871
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) THREE-CAR GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE
- Permit Issued
- Issued on 10/20/2021
- Issuing Office
- Current Status
- CofO Issued on 11/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 3/18/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 5/13/2021 | FERNANDO FLORES |
| Plan Check Approved | 9/21/2021 | SINA KHOSRAVI |
| Issued | 10/20/2021 | APPLICANT |
| Building Plans Picked Up | 10/21/2021 | APPLICANT |
| CofO in Progress | 11/3/2022 | OSVALDO PARAMO |
| CofO in Progress | 11/3/2022 | OSVALDO PARAMO |
| Permit Finaled | 11/9/2022 | DEROLD HAUFF |
| CofO Issued | 11/9/2022 | DEROLD HAUFF |
| Permit Finaled | 11/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/7/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | JEANIE LAM |
| Sewer availability | Cleared | 4/7/2021 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 4/26/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/25/2022 | Approved | SHAVONNE ESPINOZA |
| Pre-Inspection | 2/1/2022 | Approved | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/3/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/8/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/8/2022 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 3/16/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/17/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 3/17/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/23/2022 | Partial Approval | OSVALDO PARAMO |
| Insulation | 3/30/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/5/2022 | Approved | OSVALDO PARAMO |
| Final | 7/25/2022 | Corrections Issued | CRAIG VAUGHAN |
| Pool Piping | 7/25/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 8/18/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 8/18/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 10/20/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 10/20/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 11/2/2022 | OK to Issue CofO | OSVALDO PARAMO |
| Smoke Detectors | 11/2/2022 | Approved | OSVALDO PARAMO |