4025 W DON IBARRA PL 90008
Certificate Information: 4025 W DON IBARRA PL 90008
- Application / Permit
- 21016-10000-06579
- Plan Check / Job No.
- B21LA04770
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO 3 SLIDING DOORS AND REPLACE WITH 2 NEW 20' SLIDING DOOR. ALL FRAMING PER STRUTURAL ENGINEERING. NO CHANGE TO (E) SQ. FOOTAGE
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/29/2022
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2021 | ADAM HEGAZI |
| Corrections Issued | 3/17/2021 | ADAM HEGAZI |
| Plan Check Approved | 5/18/2021 | RICARDO RAMIREZ |
| Issued | 11/8/2021 | APPLICANT |
| Building Plans Picked Up | 11/9/2021 | APPLICANT |
| Permit Finaled | 6/28/2022 | ANTHONY EGSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/7/2021 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/29/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/19/2022 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/18/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/24/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/8/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/10/2022 | Approved | ANTHONY EGSON |
| Deputy Steel/Welding | 3/31/2022 | No Access for Inspection | ANTHONY EGSON |
| Structural Steel Frame | 4/1/2022 | Approved | ANTHONY EGSON |
| Final | 4/8/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/8/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 4/8/2022 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 4/8/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 5/2/2022 | Approved | ANTHONY EGSON |
| Final | 5/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 5/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/12/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/13/2022 | Approved | ANTHONY EGSON |
| Final | 6/8/2022 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 6/8/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 6/28/2022 | Permit Finaled | ANTHONY EGSON |
| Smoke Detectors | 6/28/2022 | Approved | ANTHONY EGSON |