245 S ARDMORE AVE 90004
Certificate Information: 245 S ARDMORE AVE 90004
- Application / Permit
- 21016-10000-06571
- Plan Check / Job No.
- B21LA04764
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-story addition to detached garage and convert into an ADU. PER GCS 65852.2
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- Issued on 5/12/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | JOE VO |
| Corrections Issued | 4/10/2021 | JOE VO |
| Quality Review Completed | 4/20/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 5/15/2021 | JOE VO |
| Applicant returned to address corrections | 6/7/2021 | JOE VO |
| Applicant returned to address corrections | 8/5/2021 | JOE VO |
| Plan Check Approved | 3/30/2022 | JOE VO |
| Issued | 5/12/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2021 | JEREMY CHOK |
| Construction near power lines | Cleared | 11/24/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2021 | JEREMY CHOK |
| Sewer availability | Cleared | 11/29/2021 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 1/11/2022 | JEREMY CHOK |
Contact Information
| Contractor | Vicrez Construction Co; Lic. No.: 1022661-B | 2805 PRIMERA VISTA BAKERSFIELD, CA 93306 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/16/2022 | Partial Inspection | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 6/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 6/29/2022 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/18/2022 | Corrections Issued | JEFFREY MEAD |
| METHANE-Barrier | 7/18/2022 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 7/18/2022 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/3/2022 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 9/23/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 9/23/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/13/2022 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 10/13/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/13/2022 | Corrections Issued | JEFFREY MEAD |
| METHANE-Rough | 10/13/2022 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/25/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/25/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/26/2022 | Approved | JEFFREY MEAD |
| Insulation | 10/28/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/2/2022 | Approved | JEFFREY MEAD |
| Sewer | 11/29/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 11/29/2022 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | JEFFREY MEAD |
| BUILDING-Rough-Frame | 6/8/2023 | Approved | JEFFREY MEAD |
| Final | 6/8/2023 | Partial Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/8/2023 | Approved | JEFFREY MEAD |
| Green Building Final | 6/8/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 6/8/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 6/8/2023 | Partial Approval | JEFFREY MEAD |