1546 S WILTON PL 90019

Certificate Information: 1546 S WILTON PL 90019

Application / Permit
21016-10000-06554
Plan Check / Job No.
B21LA04742
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT STORY OPEN FRONT PARKING GARAGE WITH LIVING UNITS ABOVE. INSTALL NEW (4) SPECIAL STEEL CANTILEVERED COLUMNS.
Permit Issued
Issued on 6/23/2021
Issuing Office
Current Status
CofC Issued on 9/3/2021

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 HANS SANTIAGO
Corrections Issued 4/12/2021 HANS SANTIAGO
Quality Review Completed 4/14/2021 SAI KHUM
Applicant returned to address corrections 5/5/2021 HANS SANTIAGO
Applicant returned to address corrections 5/18/2021 HANS SANTIAGO
Plan Check Approved 6/2/2021 ANDREW SANTIAGO
Issued 6/23/2021 APPLICANT
OK for CofC 9/2/2021 BRUCE CAMPBELL
CofC Issued 9/3/2021 WINSTON DUNNING

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/5/2021 JUAN ASHTON
Community Plan Implem. Overlay Cleared 5/25/2021 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 5/25/2021 THAN WIN
Tenant Habitability Plan Cleared 6/14/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/14/2021 Partial Inspection MARK FERRARI
Deputy Drilled-In Anchors 7/28/2021 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 7/28/2021 Conditional Approval MARK FERRARI
Deputy Steel/Welding 7/28/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 7/30/2021 Approved BRUCE CAMPBELL
Wood Frame 8/4/2021 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 8/12/2021 Corrections Issued DARRYL ARNOLD
Final 9/2/2021 OK for CofC BRUCE CAMPBELL
METHANE-Final 9/2/2021 Approved BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved BRUCE CAMPBELL
Smoke Detectors 9/2/2021 Approved BRUCE CAMPBELL