1555 S ST ANDREWS PL 90019

Certificate Information: 1555 S ST ANDREWS PL 90019

Application / Permit
21016-10000-06543
Plan Check / Job No.
B21LA04734
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: RETROFIT SOFT STORY OPEN FRONT PARKING GARAGE WITH LIVING UNITS ABOVE USING NEW (4) SPECIAL STEEL CANTILEVERED COLUMNS WITH GRADE BEAMS
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofC Issued on 9/19/2022

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 HANS SANTIAGO
Corrections Issued 4/5/2021 HANS SANTIAGO
Quality Review Completed 4/7/2021 SAI KHUM
Applicant returned to address corrections 4/19/2021 HANS SANTIAGO
Plan Check Approved 5/3/2021 ANDREW SANTIAGO
Issued 6/9/2021 APPLICANT
OK for CofC 9/19/2022 MARK FERRARI
CofC Issued 9/19/2022 WINSTON DUNNING

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 4/12/2021 RAFAEL FONTES
Community Plan Implem. Overlay Cleared 4/15/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/19/2021 WALLIE JONG
Tenant Habitability Plan Cleared 5/27/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/29/2021 Conditional Approval BRUCE CAMPBELL
Footing/Foundation/Slab 7/14/2021 Approved MARK FERRARI
Deputy Reinf. Concrete 7/15/2021 Conditional Approval MARK FERRARI
Wood Frame 7/26/2021 Approved DARRYL ARNOLD
Deputy Wood Construction 7/29/2021 Conditional Approval MARK FERRARI
Wood Frame 7/30/2021 Approved BRUCE CAMPBELL
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Approved MARK FERRARI
Interior/Exterior Lathing 8/16/2021 Approved MARK FERRARI
Final 8/30/2021 Conditional Approval MARK FERRARI
METHANE-Final 8/30/2021 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/30/2021 SGSOV Approved MARK FERRARI
Smoke Detectors 8/30/2021 Approved MARK FERRARI
Final 9/19/2022 OK for CofC MARK FERRARI