2830 1/2 W AVENUE 33 90065
Certificate Information: 2830 1/2 W AVENUE 33 90065
- Application / Permit
- 21016-10000-06487
- Plan Check / Job No.
- B21LA04698
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AN EXISTING GARAGE INTO AN ADU
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/15/2021 | RICARDO RAMIREZ |
| Corrections Issued | 3/15/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 6/2/2021 | SINA KHOSRAVI |
| Issued | 6/25/2021 | APPLICANT |
| Building Plans Picked Up | 6/30/2021 | APPLICANT |
| CofO in Progress | 11/4/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/9/2022 | DEROLD HAUFF |
| CofO Issued | 11/9/2022 | DEROLD HAUFF |
| Permit Finaled | 11/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 3/31/2021 | RENZ SORIANO |
| Supp. Use District POD/CDO/TDO | Cleared | 4/8/2021 | ADRINEH MELKONIAN |
| ZI | Cleared | 4/8/2021 | ADRINEH MELKONIAN |
| Hydrant and Access approval | Cleared | 4/25/2021 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 5/10/2021 | BRIAN MILLER |
Contact Information
| Contractor | Mondragon Construction; Lic. No.: 847728-B | 6714 CLEON AVENUE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1620 CENTINELA AVE 3048 INGLEWOOD, CA 90302 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/19/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 7/19/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/7/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/7/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 9/7/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 9/7/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 9/7/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/22/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/28/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/25/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Rough-Elec/Plmb/HVAC | 10/25/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Wood Frame | 10/25/2021 | Partial Approval | ADAM ESCOTO |
| Footing/Foundation/Slab | 10/27/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/27/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/2/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2022 | Approved | AMY COLIN |
| Insulation | 1/6/2022 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 1/6/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/27/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/27/2022 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 1/27/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 2/7/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 10/21/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/21/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 10/21/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV No Gas | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/21/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 11/3/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 11/3/2022 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 11/3/2022 | Approved | HAMIK HARTOUNIAN |