3824 S KEYSTONE AVE 1-8 90232

Certificate Information: 3824 S KEYSTONE AVE 1-8 90232

Application / Permit
21016-10000-06477
Plan Check / Job No.
B21LA04678
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) ATTACHED 1 CAR CARPORT IN FRONT OF EXISTING/ MULTIFAMILY BUILDING TO ONE (1) ATTACHED ADU PER GCS 65852.2 (e)(1)(C)
Permit Issued
Issued on 7/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/16/2021 LUKE GONZALES
Corrections Issued 3/17/2021 LUKE GONZALES
Building Plans Picked Up 3/19/2021 APPLICANT
Applicant returned to address corrections 7/13/2021 TSE MING HUANG
Plan Check Approved 4/26/2022 MINA HABILI
Issued 7/5/2022 APPLICANT
CofO in Progress 3/14/2024 FARHAD DADBIN
Permit Finaled 3/18/2024 DAVID TSAU
CofO Issued 3/18/2024 DAVID TSAU
Permit Finaled 3/18/2024 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 3/22/2021 DENNIS BRAGIN
Sewer availability Cleared 3/22/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 3/23/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 5/28/2021 JOHN CONNEALLY

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/9/2022 Approved PAUL DAVIDSON
Footing/Foundation/Slab 10/18/2022 Approved DAVID TSAU
METHANE-Rough 12/1/2022 Not Ready for Inspection GRANT WOODS
Wood Frame 12/1/2022 Not Ready for Inspection GRANT WOODS
METHANE-Rough 1/6/2023 Partial Approval FARHAD DADBIN
Wood Frame 1/6/2023 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 4/28/2023 Approved FARHAD DADBIN
Insulation 8/16/2023 Not Ready for Inspection FARHAD DADBIN
Insulation 9/18/2023 Approved FARHAD DADBIN
Drywall Nailing 9/26/2023 Approved FARHAD DADBIN
Interior/Exterior Lathing 9/26/2023 Approved FARHAD DADBIN
Final 2/23/2024 OK to Issue CofO FARHAD DADBIN
METHANE-Final 2/23/2024 Approved FARHAD DADBIN
METHANE-Rough 2/23/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 2/23/2024 Approved FARHAD DADBIN
Wood Frame 2/23/2024 Approved FARHAD DADBIN