3824 S KEYSTONE AVE 1-8 90232
Certificate Information: 3824 S KEYSTONE AVE 1-8 90232
- Application / Permit
- 21016-10000-06477
- Plan Check / Job No.
- B21LA04678
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) ATTACHED 1 CAR CARPORT IN FRONT OF EXISTING/ MULTIFAMILY BUILDING TO ONE (1) ATTACHED ADU PER GCS 65852.2 (e)(1)(C)
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2021 | LUKE GONZALES |
| Corrections Issued | 3/17/2021 | LUKE GONZALES |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| Applicant returned to address corrections | 7/13/2021 | TSE MING HUANG |
| Plan Check Approved | 4/26/2022 | MINA HABILI |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 3/14/2024 | FARHAD DADBIN |
| Permit Finaled | 3/18/2024 | DAVID TSAU |
| CofO Issued | 3/18/2024 | DAVID TSAU |
| Permit Finaled | 3/18/2024 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 3/22/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2021 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 5/28/2021 | JOHN CONNEALLY |
Contact Information
| Architect | Feld,, Dovid Yitzchak; Lic. No.: C37588 | 921 S HOLT AVENUE LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2022 | Approved | PAUL DAVIDSON |
| Footing/Foundation/Slab | 10/18/2022 | Approved | DAVID TSAU |
| METHANE-Rough | 12/1/2022 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 12/1/2022 | Not Ready for Inspection | GRANT WOODS |
| METHANE-Rough | 1/6/2023 | Partial Approval | FARHAD DADBIN |
| Wood Frame | 1/6/2023 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 4/28/2023 | Approved | FARHAD DADBIN |
| Insulation | 8/16/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 9/18/2023 | Approved | FARHAD DADBIN |
| Drywall Nailing | 9/26/2023 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 9/26/2023 | Approved | FARHAD DADBIN |
| Final | 2/23/2024 | OK to Issue CofO | FARHAD DADBIN |
| METHANE-Final | 2/23/2024 | Approved | FARHAD DADBIN |
| METHANE-Rough | 2/23/2024 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 2/23/2024 | Approved | FARHAD DADBIN |
| Wood Frame | 2/23/2024 | Approved | FARHAD DADBIN |