18401 W LASSEN ST 91325
Certificate Information: 18401 W LASSEN ST 91325
- Application / Permit
- 21016-10000-06474
- Plan Check / Job No.
- B21LA04675
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- REMOVE EXISTING GENERATOR AND TANK. INSTALL NEW GENERAC 25 KW DIESEL GENERATOR WITH TANK IN NEW LEASE AREA EXPANSION. 8ft HIGH CMU WALL INCLOSURE PER ENGINEER DESIGH
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2022
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2021 | RAHEL BEYENE |
| Corrections Issued | 3/16/2021 | RAHEL BEYENE |
| Plan Check Approved | 6/23/2021 | CELESTE NGUYEN |
| Issued | 1/10/2022 | APPLICANT |
| Building Plans Picked Up | 1/11/2022 | APPLICANT |
| Permit Finaled | 11/29/2022 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| ZA Case | Cleared | 6/15/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 6/15/2021 | CLAUDE GOODING |
Contact Information
| Contractor | Diversified Communications Services Inc; Lic. No.: 540890-B | 1260 PIONEER ST BREA, CA 92821 |
| Engineer | Bronnenkant,, Adam; Lic. No.: C74190 | 23650 N 84TH PL SCOTTSDALE, AZ 85255 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/19/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 1/20/2022 | Conditional Approval | JEFFREY FULTON |
| Reinforced Masonry Frame | 1/24/2022 | Approved | JEFFREY FULTON |
| Deputy Reinf. Masonry | 1/25/2022 | Conditional Approval | JEFFREY FULTON |
| Final | 2/8/2022 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 2/8/2022 | Approved | JEFFREY FULTON |
| Final | 9/13/2022 | Corrections Issued | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Approved | JEFFREY FULTON |
| Final | 11/29/2022 | Permit Finaled | DEANDRE HOFFMAN |