10403 N HILLHAVEN AVE 91042
Certificate Information: 10403 N HILLHAVEN AVE 91042
- Application / Permit
- 21016-10000-06442
- Plan Check / Job No.
- B21LA04650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Conversion of an (E) detached 2-car garage into an ADU per state law GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 1/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2021 | HELEN NGUYEN |
| Corrections Issued | 3/16/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/14/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/23/2021 | HELEN NGUYEN |
| Plan Check Approved | 5/3/2021 | HELEN NGUYEN |
| Issued | 5/10/2021 | APPLICANT |
| CofO in Progress | 12/7/2021 | MATTHEW NELSON |
| CofO Issued | 1/22/2022 | MICHAEL SMITH |
| Permit Finaled | 1/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/19/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2021 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 3/31/2021 | KORA MCNAUGHTON |
| Grading Pre-Inspection | Cleared | 4/1/2021 | BRIAN MILLER |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91206 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/13/2021 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/13/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 7/13/2021 | Partial Approval | MATTHEW NELSON |
| Sewer | 7/13/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 7/28/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 7/28/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/30/2021 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 7/30/2021 | Partial Approval | WILLIAM KUEHN |
| Wood Frame | 7/30/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 8/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 8/12/2021 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 8/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/20/2021 | Partial Approval | MATTHEW NELSON |
| Gas Test | 8/20/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/20/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/20/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 8/20/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 8/20/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2021 | Approved | MATTHEW NELSON |
| Insulation | 8/27/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/3/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/10/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Shower Pan | 9/10/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/16/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 10/20/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/22/2021 | Approved | MATTHEW NELSON |
| Final | 11/22/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 11/22/2021 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 11/22/2021 | Approved | MATTHEW NELSON |
| Final | 12/1/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/1/2021 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/1/2021 | SGSOV Not Ready | MATTHEW NELSON |
| ELECTRICAL-Final | 12/7/2021 | Approved | MATTHEW NELSON |
| Final | 12/7/2021 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 12/7/2021 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/7/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/7/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Approved | MATTHEW NELSON |