718 S HILL ST 90014

Certificate Information: 718 S HILL ST 90014

Application / Permit
21016-10000-06399
Plan Check / Job No.
B21LA04624
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
CHANGE OF USE OF UNOCCUPIES ROOF TO OUTDOOR BAR/LOUNGE.ADD RESTROOMS ON THE ROOF TOP. THE WORK WILL INCLUDE A NEW ROOF DECK STRUCTURE AND HIGH-RISE UPGRADES. Bar/Lounge is core and shell only. See comments.
Permit Issued
Issued on 10/11/2022
Issuing Office
Current Status
Issued on 10/11/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/12/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 LARRY LEE
Green Plans Picked Up 3/23/2021 APPLICANT
Corrections Issued 3/25/2021 LARRY LEE
Quality Review Completed 3/31/2021 CHARLES CHANG
Building Plans Picked Up 4/5/2021 APPLICANT
Disabled Access Plans Picked Up 4/12/2021 APPLICANT
Applicant returned to address corrections 5/13/2021 LARRY LEE
Applicant returned to address corrections 5/14/2021 LARRY LEE
Applicant returned to address corrections 5/24/2021 LARRY LEE
Applicant returned to address corrections 6/21/2021 LARRY LEE
Applicant returned to address corrections 9/27/2021 LARRY LEE
Applicant returned to address corrections 10/5/2021 LARRY LEE
Applicant returned to address corrections 12/9/2021 LARRY LEE
Applicant returned to address corrections 6/3/2022 LARRY LEE
Applicant returned to address corrections 8/17/2022 LARRY LEE
Applicant returned to address corrections 10/6/2022 CHUNG-WEN CHUANG
Plan Check Approved 10/7/2022 CHUNG-WEN CHUANG
Issued 10/11/2022 APPLICANT

Permit Application Clearance Information

Highway dedication Cleared 4/13/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 4/13/2021 JEANIE LAM
"D" conditions Cleared 4/14/2021 TERRI OSBORNE
ZA Case Cleared 4/14/2021 TERRI OSBORNE
Eng Process Fee Ord 176,300 Cleared 4/21/2021 JEANIE LAM
Miscellaneous Cleared 4/23/2021 NAOMI GUTH
ZA Case Cleared 4/23/2021 NAOMI GUTH
Miscellaneous Cleared 4/27/2021 DAVID URITA
CPC Cleared 4/28/2021 TERRI OSBORNE
Comm Cor/Mini-Mall Cleared 4/28/2021 TERRI OSBORNE
Redevelopment Project Area Cleared 4/29/2021 DAVID URITA
Sewer availability Cleared 4/29/2021 JEANIE LAM
ZA Case Cleared 5/3/2021 NAOMI GUTH
Building over 36-ft Cleared 5/12/2021 CALOSHA APPROVED
Bicycle Parking Cleared 12/14/2021 JEREMY CHOK
Green Code Cleared 2/1/2022 AARON COSTA
Food Service Establishment Cleared 4/26/2022 KENNETH BROWNE
Hydrant and Access approval Cleared 4/26/2022 KURT CORRAL
Fire Marshal Fire Life Safety Cleared 8/5/2022 DOMINIQUE MEDINA
DAS Clearance Cleared 8/24/2022 LARRY LEE

Contact Information

Contractor Gundry Partners Lp; Lic. No.: 1006248-B 17434 BELLFLOWER BLVD   SUITE 300    BELLFLOWER, CA 90706

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 10/21/2022 Corrections Issued KATY RAMIREZ
Structural Steel Frame 11/4/2022 Partial Inspection KATY RAMIREZ
Pre-Inspection 12/15/2022 Partial Inspection KATY RAMIREZ
Structural Steel Frame 2/2/2023 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 2/21/2023 Corrections Issued KATY RAMIREZ
Interior/Exterior Lathing 3/13/2023 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/13/2023 No Access for Inspection KATY RAMIREZ
Light Gage Steel Frame 3/16/2023 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 3/23/2023 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 4/3/2023 Partial Approval RAMAZANALI ALMASI
Wood Frame 4/3/2023 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 4/4/2023 No Access for Inspection VAHE KELEDJIAN
Wood Frame 4/7/2023 Partial Approval MARTIN TAVITIAN
Insulation 4/10/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 4/13/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 4/18/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 4/18/2023 Approved RAMAZANALI ALMASI
Light Gage Steel Frame 4/26/2023 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 5/2/2023 Partial Approval KATY RAMIREZ
Drywall Nailing 5/18/2023 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 5/30/2023 Approved RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved RAMAZANALI ALMASI
Structural Steel Frame 5/30/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 6/1/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 6/26/2023 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 6/28/2023 Partial Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Corrections Issued KATY RAMIREZ
Special/Order Compliance 8/7/2023 Partial Inspection KATY RAMIREZ
Special/Order Compliance 3/5/2024 Partial Approval LUIS CCAMACHO
Special/Order Compliance 7/16/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/25/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/30/2024 Partial Approval LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Not Ready LUIS CCAMACHO
Drywall Nailing 8/2/2024 Not Ready for Inspection LUIS CCAMACHO
Final 5/20/2026 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 5/20/2026 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 5/20/2026 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 5/20/2026 Not Ready for Inspection JEROME BLACKWOOD
Reinforced Concrete Frame 5/20/2026 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 5/20/2026 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 5/20/2026 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Not Ready PAUL BAZERKANIAN