4549 N VARNA AVE 91423

Certificate Information: 4549 N VARNA AVE 91423

Application / Permit
21016-10000-06329
Plan Check / Job No.
B21LA04590
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-PLAN: CONVERTING THE EXISTING GARAGE TO AN ADU
Permit Issued
Issued on 4/3/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/14/2021 LARRY LEE
Corrections Issued 3/14/2021 LARRY LEE
Plan Check Approved 3/20/2021 LARRY LEE
Issued 4/3/2021 APPLICANT
CofO in Progress 3/21/2022 MISAEL ESPARZA
CofO Issued 5/4/2022 MICHAEL SMITH
Permit Finaled 5/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/16/2021 JOHN TRIANTAFYLLOS
ZI Cleared 3/17/2021 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/23/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 11/24/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/29/2021 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 12/1/2021 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/2/2021 Not Ready for Inspection MISAEL ESPARZA
Sewer 12/2/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/7/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/7/2021 Approved MISAEL ESPARZA
HVAC-Rough 12/7/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 12/7/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/21/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/21/2021 Approved MISAEL ESPARZA
Green Building Rough 12/21/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 12/21/2021 Approved MISAEL ESPARZA
Insulation 12/27/2021 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 12/27/2021 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 12/29/2021 Approved JACK KARGODORIAN
Drywall Nailing 1/3/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 1/3/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/5/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 3/15/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/15/2022 Corrections Issued MISAEL ESPARZA
Final 3/15/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 3/15/2022 Approved MISAEL ESPARZA
Green Building Rough 3/15/2022 Approved MISAEL ESPARZA
HVAC-Final 3/15/2022 Approved MISAEL ESPARZA
MERV13>=Final 3/15/2022 Approved MISAEL ESPARZA
PLUMBING-Final 3/15/2022 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/15/2022 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 3/15/2022 Approved MISAEL ESPARZA
ELECTRICAL-Final 3/18/2022 Approved MISAEL ESPARZA
Final 3/18/2022 OK to Issue CofO MISAEL ESPARZA
PLUMBING-Final 3/18/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/18/2022 SGSOV Approved MISAEL ESPARZA