101 S THE GROVE DR 90036
Certificate Information: 101 S THE GROVE DR 90036
- Application / Permit
- 21016-10000-06281
- Plan Check / Job No.
- B21LA04554
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TENANT IMPROVEMENT TO (E) RESTAURANT - REMODEL DINING ROOM, BAR AREAS, RESTROOMS, ADD NEW ESCALATOR, AWNINGS, ALL NEW STRUCTURAL WORK PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 3/18/2022
Permit Application Status History
| Submitted | 3/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | SAM CHANG |
| Green Plans Picked Up | 3/23/2021 | APPLICANT |
| Corrections Issued | 3/31/2021 | SAM CHANG |
| Quality Review Completed | 4/5/2021 | EUGENE BARBEAU |
| Disabled Access Plans Picked Up | 4/12/2021 | APPLICANT |
| Applicant returned to address corrections | 5/26/2021 | SAM CHANG |
| Applicant returned to address corrections | 7/9/2021 | SAM CHANG |
| Plan Check Approved | 8/10/2021 | SAM CHANG |
| Issued | 8/25/2021 | APPLICANT |
| Building Plans Picked Up | 8/27/2021 | APPLICANT |
| Permit Finaled | 3/18/2022 | KATY RAMIREZ |
Permit Application Clearance Information
| "D" conditions | Cleared | 6/16/2021 | RICHARD REASER |
| "T" removal | Cleared | 6/16/2021 | RICHARD REASER |
| ZA Case | Cleared | 6/16/2021 | RICHARD REASER |
| ZA Case | Cleared | 6/16/2021 | RICHARD REASER |
| ZA Case | Cleared | 6/16/2021 | RICHARD REASER |
| Fire Marshal Fire Life Safety | Cleared | 6/23/2021 | VIDAL GARCIA |
| DAS Clearance | Cleared | 6/24/2021 | SAM CHANG |
| Green Code | Cleared | 7/1/2021 | AARON COSTA |
| Food Service Establishment | Cleared | 7/29/2021 | PAWAN VERMA |
| Food establishment approval | Cleared | 8/10/2021 | LACDHS APPROVED |
Contact Information
| Architect | Calnon,, Robert Andrew; Lic. No.: C26387 | 8840 WARNER AVE #100A FOUNTAIN VALLEY, CA 92708 |
| Contractor | Shawmut Woodworking & Supply Inc; Lic. No.: 747583-B | 560 HARRISON AVENUE BOSTON, MA 02118 |
| Engineer | Black,, Ian Robert; Lic. No.: S5505 | 19401 OLANA LN HUNTINGTON BEACH, CA 92646 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 9/21/2021 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 9/27/2021 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 9/27/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 10/1/2021 | Partial Approval | JONATHAN QUACH |
| Drywall Nailing | 10/5/2021 | Partial Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 11/1/2021 | Approved | JONATHAN QUACH |
| Light Gage Steel Frame | 11/10/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 11/15/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 11/18/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 11/30/2021 | Partial Approval | KATY RAMIREZ |
| Pre-Inspection | 1/10/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 1/14/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Final | 3/10/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 3/10/2022 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 3/10/2022 | Approved | KATY RAMIREZ |
| Final | 3/16/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 3/18/2022 | Permit Finaled | KATY RAMIREZ |