550 S HOPE ST 90071
Certificate Information: 550 S HOPE ST 90071
- Application / Permit
- 21016-10000-06259
- Plan Check / Job No.
- B21LA04515
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- eplan. NEW FREE-STANDING SEATING AREA LOBBY RENOVATION INCLUDES NEW RECEPTION MILLWORK DESK, NEW MEDIA WALL, WALL FINISH UPDATES AND FURNITURE SEATING.
- Permit Issued
- Issued on 6/11/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/3/2022
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2021 | MONICA RAMIREZ |
| Corrections Issued | 3/22/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 5/19/2021 | MONICA RAMIREZ |
| Plan Check Approved | 5/26/2021 | MONICA RAMIREZ |
| Issued | 6/11/2021 | APPLICANT |
| Permit Finaled | 5/2/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 5/13/2021 | MENOA AGHAJANI |
Contact Information
| Architect | Guieb,, Melvin B; Lic. No.: C36943 | 30106 N CAMBRIDGE AVENUE CASTAIC, CA 91384 |
| Contractor | Snyder Langston Llc; Lic. No.: 1019188-B | 17962 COWAN IRVINE, CA 92614 |
| Engineer | Youssef,, Nabih Fouad Guirg; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 9/8/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Drilled-In Anchors | 9/9/2021 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 9/27/2021 | Approved | TIMOTHY BUXTON |
| Structural Steel Frame | 9/27/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/1/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 10/6/2021 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 11/15/2021 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 2/1/2022 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 3/1/2022 | Approved | TIMOTHY BUXTON |
| Final | 5/2/2022 | Permit Finaled | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 5/2/2022 | Approved | TIMOTHY BUXTON |