237 E 76TH ST 90003

Certificate Information: 237 E 76TH ST 90003

Application / Permit
21016-10000-06236
Plan Check / Job No.
B21LA04481
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO A NEW ADU PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/30/2021 SAMUEL GONZALEZ
Corrections Issued 3/31/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 6/8/2021 JESSE JIMENEZ
Plan Check Approved 9/23/2021 RICARDO RAMIREZ
Issued 10/18/2021 APPLICANT
Building Plans Picked Up 10/19/2021 APPLICANT
CofO in Progress 10/27/2022 LILIANA PORTILLO
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/22/2021 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 6/22/2021 JEREMY CHOK
Sewer availability Cleared 6/22/2021 JEREMY CHOK
Hydrant and Access approval Cleared 8/31/2021 JOHN CONNEALLY
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY

Contact Information

Contractor Kashmal Group Of America Inc; Lic. No.: 592828-B 2100 SOUTH FIGUEROA #326      LOS ANGELES, CA 90007

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 1/26/2022 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 2/9/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 2/9/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 2/9/2022 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/14/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Approved LILIANA PORTILLO
Green Building Rough 2/14/2022 Approved LILIANA PORTILLO
HVAC-Rough 2/14/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 2/14/2022 Approved LILIANA PORTILLO
Insulation 2/17/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/17/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 2/23/2022 Approved LILIANA PORTILLO
HVAC-Rough 2/23/2022 Corrections Issued LILIANA PORTILLO
Shower Pan 2/23/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 3/30/2022 Not Ready for Inspection LILIANA PORTILLO
Final 3/30/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 3/30/2022 Corrections Issued LILIANA PORTILLO
HVAC-Final 3/30/2022 Approved LILIANA PORTILLO
HVAC-Rough 3/30/2022 Approved LILIANA PORTILLO
PLUMBING-Final 3/30/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 3/30/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/1/2022 Approved LILIANA PORTILLO
Final 6/1/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 6/1/2022 Approved LILIANA PORTILLO
PLUMBING-Final 6/1/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/1/2022 SGSOV Approved LILIANA PORTILLO
Final 10/26/2022 OK to Issue CofO LILIANA PORTILLO