1360 S WESTWOOD BLVD 90024
Certificate Information: 1360 S WESTWOOD BLVD 90024
- Application / Permit
- 21016-10000-06130
- Plan Check / Job No.
- B21LA04374
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- STRUCTURAL FOUNDATIONS & COLUMNS & BEAMS UPGRADE TO (E) RETAIL BUILDING.
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | ZAW HAN |
| Corrections Issued | 3/17/2021 | GARO TELMI |
| Quality Review Completed | 3/22/2021 | KEN GILL |
| Building Plans Picked Up | 3/22/2021 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | GARO TELMI |
| Plan Check Approved | 6/8/2021 | GARO TELMI |
| Issued | 6/18/2021 | APPLICANT |
| Permit Finaled | 3/28/2024 | PAUL DAVIDSON |
Permit Application Clearance Information
| Supp. Use District POD/CDO/TDO | Cleared | 4/29/2021 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 6/8/2021 | GARO TELMI |
Contact Information
| Contractor | Andres Construction; Lic. No.: 811901-B | 663 AZARA PLACE SUNNYVALE, CA 94086 |
| Engineer | Bushra,, Rafeek L; Lic. No.: S4490 | 2564 W WOODLAND DR ANAHEIM, CA 92801 |
| Engineer | Sivathasan,, Kathiravetpilla; Lic. No.: GE2708 | 831 LA DOCENA LANE CORONA, CA 92879 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2021 | Partial Inspection | JOHN DODGE |
| Deputy Steel/Welding | 7/19/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/22/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/23/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 8/2/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 8/3/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 8/4/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 8/26/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 8/27/2021 | Approved | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 10/15/2021 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Partial Approval | JEFF BYTHEWAY |
| Footing/Foundation/Slab | 10/21/2021 | Not Ready for Inspection | JEFF BYTHEWAY |
| Structural Steel Frame | 10/21/2021 | Partial Approval | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 10/29/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 11/2/2021 | Conditional Approval | PAUL DAVIDSON |
| Structural Steel Frame | 11/9/2021 | Partial Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 11/17/2021 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 11/17/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Fireproofing | 12/1/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/7/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/8/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/9/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/10/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/13/2021 | Conditional Approval | JOHN DODGE |
| Deputy Fireproofing | 12/16/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/17/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/21/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/22/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/23/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/27/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 12/28/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 1/4/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 1/5/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/6/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 1/7/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 1/31/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 2/9/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 2/25/2022 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 3/11/2022 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 3/11/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Fireproofing | 4/4/2022 | Conditional Approval | JOHN DODGE |
| Structural Steel Frame | 4/11/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Partial Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 4/12/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Reinforced Concrete Frame | 4/14/2022 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 8/18/2023 | Conditional Approval | SORIN CIRSTOIU |