1509 S ORANGE GROVE AVE 90019
Certificate Information: 1509 S ORANGE GROVE AVE 90019
- Application / Permit
- 21016-10000-06124
- Plan Check / Job No.
- B21LA04366
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: USING 1 STEEL SPECIAL CANTILEVER COLUMN
- Permit Issued
- Issued on 8/12/2021
- Issuing Office
- Current Status
- OK for CofC on 9/16/2021
Permit Application Status History
| Submitted | 3/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | DANIEL SANJUAN |
| Corrections Issued | 4/9/2021 | DANIEL SANJUAN |
| Quality Review Completed | 4/20/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 5/19/2021 | DANIEL SANJUAN |
| Plan Check Approved | 6/2/2021 | DANIEL SANJUAN |
| Issued | 8/12/2021 | APPLICANT |
| OK for CofC | 9/15/2021 | DARRYL ARNOLD |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/2/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Zebra Construction Inc; Lic. No.: 1055609-B | , |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: NA84559 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2021 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/2/2021 | Order to Comply Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/2/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Structural Steel Frame | 9/2/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 9/2/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 9/3/2021 | Conditional Approval | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 9/3/2021 | Approved | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 9/3/2021 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 9/3/2021 | Approved | BRUCE CAMPBELL |
| Wood Frame | 9/3/2021 | Approved | BRUCE CAMPBELL |
| Drywall Nailing | 9/7/2021 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 9/7/2021 | Approved | MARK FERRARI |
| Final | 9/15/2021 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Final | 9/15/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 9/15/2021 | Approved | DARRYL ARNOLD |